Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work

32 mm dia nominal bore

Item number
18.12.4
Analysis basis
Details of cost for 10 metre
Priced inputs
6
Derived rate
540.30 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.12.4 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work 32 mm dia nominal bore — is derived from 6 priced inputs for 10 metre and works out to ₹540.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Weight for carriage = pipe weight + 2%
  • for fiitings = 1.02 * 31.70 = 32 kg = 0.032
  • tonne
  • Trenching and refilling etc.
CodeInputUnitQuantityRate (INR)Amount (INR)
1548G.I. pipes 32 mm diaMaterialmetre10.2247.002,519.40
9999White lead, hemp, oil etc.MaterialL.S.6.762.2715.35
0116Fitter (grade 1)Labourday0.12897.00107.64
0114BeldarLabourday0.25736.00184.00
0114BeldarLabourday0.66736.00485.76
0115CoolieLabourday0.66736.00485.76
TOTAL
3,797.91
Add 1 % Water charges on “W”
37.98
TOTAL
3,835.89
Add GST on “X” (multiplying factor 0.2127)
815.89
TOTAL
4,651.78
Add 15% CPOH on “Y”
697.77
TOTAL
5,349.55
Add Cess @ 1% on “Z”
53.50
Cost of 10 metre
5,403.05
Cost of 1 metre
540.31
Say
540.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1432. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.