Skip to main content

CPWD Analysis of Rates · Water Supply

Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Female Transition Elbow / FTE

For 15mm outer dia X 1/2” nominal dia threaded

Item number
18.105.1
Analysis basis
Details of cost for 1 no.
Priced inputs
1
Derived rate
1,031.40 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.105.1 Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Female Transition Elbow / FTE For 15mm outer dia X 1/2” nominal dia threaded — is derived from 1 priced inputs for 1 no and works out to ₹1,031.40 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
3971Stainless steel Female Transition Elbow / FTE for 15mm outer dia X 1/2” nominal dia threaded of grade 316L as per IS 6911:2017 and conforming to EN-10312SS Female Transition Elbow/ FTE for 15 mm outer dia X 1/2” nominal dia threaded of grade 316L as per IS 6911:2017 and conforming to EN-10312 standardMaterialeach1725.00725.00
TOTAL
725.00
Add 1 % Water charges on “W”
7.25
TOTAL
732.25
Add GST on “X” (multiplying factor 0.2127)
155.75
TOTAL
888.00
Add 15% CPOH on “Y”
133.20
TOTAL
1,021.20
Add Cess @ 1% on “Z”
10.21
Cost of 1 no.
1,031.41
Say
1,031.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1688. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works