Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Male Union
- Item number
- 18.103.5
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹3,001.75/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.103.5 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Male Union For 35mm outer dia X 1-1/4” nominal dia threaded) is derived from 1 priced inputs for 1 no and works out to ₹3,001.75 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3966 | MAT | Stainless steel Male Union for 35mm outer dia X 1-1/4” nominal dia threaded of grade 316L as per IS 6911:2017 and conforming to EN-10312SS Male Union for 35 mm outer dia X 1-1/4” nominal dia threaded of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard | each | 1 | 2,110.00 | 2,110.00 |
- TOTAL
- 2,110.00
- Add 1 % Water charges on “W”
- +21.10
- TOTAL
- 2,131.10
- Add GST on “X” (multiplying factor 0.2127)
- +453.28
- TOTAL
- 2,584.38
- Add 15% CPOH on “Y”
- +387.66
- TOTAL
- 2,972.04
- Add Cess @ 1% on “Z”
- +29.72
- Cost of 1 no.
- 3,001.76
- SAY
- ₹3,001.75
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1686
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1686. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.