Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Cap
- Item number
- 18.101A.6
- Analysis basis
- 1 no
- Priced inputs
- 1
- Derived rate
- ₹2,738.55/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.101A.6 (Providing and fixing required Stainless Steel Fitting of press fit design of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard with V-profile and with O-ring sealing gasket of EPDM material of required dia as per direction of Engineer-in-charge. Cap For 54 mm outer dia pipe) is derived from 1 priced inputs for 1 no and works out to ₹2,738.55 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 3958 | MAT | Stainless steel Cap for 54 mm outer dia pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312Stainless steel Cap for 54 mm outer dia pipe of grade 316L as per IS 6911:2017 and conforming to EN-10312 standard | each | 1 | 1,925.00 | 1,925.00 |
- TOTAL
- 1,925.00
- Add 1 % Water charges on “W”
- +19.25
- TOTAL
- 1,944.25
- Add GST on “X” (multiplying factor 0.2127)
- +413.54
- TOTAL
- 2,357.79
- Add 15% CPOH on “Y”
- +353.67
- TOTAL
- 2,711.46
- Add Cess @ 1% on “Z”
- +27.11
- Cost of 1 no.
- 2,738.57
- SAY
- ₹2,738.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1682
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1682. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.