Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and making good the walls etc. Internal work - Exposed on wall
- Item number
- 18.10.4
- Analysis basis
- 10 metre
- Priced inputs
- 6
- Derived rate
- ₹667.00/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.10.4 (Providing and fixing G.I. pipes complete with G.I. fittings and clamps, including cutting and making good the walls etc. Internal work - Exposed on wall 32 mm dia nominal bore) is derived from 6 priced inputs for 10 metre and works out to ₹667.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Weight for carriage = pipe weight + 15%
- for fiitings = 1.15 * 31.70 = 36 kg = 0.036
- tonne
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1548 | MAT | G.I. pipes 32 mm dia | metre | 11.5 | 247.00 | 2,840.50 |
| 9999 | MAT | White lead, hemp, oil etc. | L.S. | 9.49 | 2.27 | 21.54 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 4.16 | 2.27 | 9.44 |
| 0116 | LAB | Fitter (grade 1) | day | 0.33 | 897.00 | 296.01 |
| 0117 | LAB | Assistant Fitter or 2nd class Fitter | day | 0.98 | 816.00 | 799.68 |
| 0114 | LAB | Beldar | day | 0.98 | 736.00 | 721.28 |
- TOTAL
- 4,688.45
- Add 1 % Water charges on “W”
- +46.88
- TOTAL
- 4,735.33
- Add GST on “X” (multiplying factor 0.2127)
- +1,007.20
- TOTAL
- 5,742.53
- Add 15% CPOH on “Y”
- +861.38
- TOTAL
- 6,603.91
- Add Cess @ 1% on “Z”
- +66.04
- Cost of 10 metre
- 6,669.95
- Cost of 1 metre
- 667.00
- SAY
- ₹667.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1427
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1427. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.