CPWD Analysis of Rates · Water Supply

Providing and fixing Polyethelene-Aluminium-Polyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with clamps at 1.00 metre spacing. This includes testing of joints complete as per direction of the Engineer-in-charge. INTERNAL WORK - EXPOSED ON WALL

1216 (16 mm OD) pipe

Item number
18.1.1
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
286.75 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 18.1.1 Providing and fixing Polyethelene-Aluminium-Polyethelene PE-AL-PE Composite Pressure Pipes conforming to IS - 15450, U.V. stabilized with carbon black having thermal stability for hot & cold water supply, capable to withstand temperature up to 80°C, including all special fittings of composite material (engineering plastic blend and brass inserts wherever required) e.g. elbows, tees, reducers, couplers & connectors etc., with clamps at 1.00 metre spacing. This includes testing of joints complete as per direction of the Engineer-in-charge. INTERNAL WORK - EXPOSED ON WALL 1216 (16 mm OD) pipe — is derived from 5 priced inputs for 10 metre and works out to ₹286.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 30 x P / 100
CodeInputUnitQuantityRate (INR)Amount (INR)
83001216 mm PE-AL-PE Composit pressure pipe1216 mm PE-AL-PE Composite pressure pipeMaterialmetre1053.00530.00
9999Cement, sand and gritMaterialL.S.2.732.276.20
0116Fitter (grade 1)Labourday0.33897.00296.01
0117Assistant Fitter or 2nd class FitterLabourday0.66816.00538.56
0114BeldarLabourday0.66736.00485.76
Add 30% for fittings and wastage etc. on (P)
159.00
TOTAL
2,015.53
Add 1 % Water charges on “W”
20.16
TOTAL
2,035.69
Add GST on “X” (multiplying factor 0.2127)
432.99
TOTAL
2,468.68
Add 15% CPOH on “Y”
370.30
TOTAL
2,838.98
Add Cess @ 1% on “Z”
28.39
Cost of 10 metre
2,867.37
Cost of 1 metre
286.74
Say
286.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1395. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.