CPWD Analysis of Rates · Water Proofing

Providing and laying six courses water proofing treatment with bitumen felt over roofs consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45, 1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt type 2 grade I (fibre base self finished bitumen felt) six and final courses of stone grit 6 mm and down size or pea sized gravel spread at 6 cubic decimeter per sqm including preparation of surface, excluding grading, compete

Item number
22.10
Analysis basis
Details of cost for 30 sqm
Priced inputs
9
Derived rate
910.85 / Sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 22.10 Providing and laying six courses water proofing treatment with bitumen felt over roofs consisting of first, third and fifth courses of blown or / and residual bitumen applied hot at 1.45, 1.20 and 1.70 kg per square metre of area respectively, second and fourth courses of roofing felt type 2 grade I (fibre base self finished bitumen felt) six and final courses of stone grit 6 mm and down size or pea sized gravel spread at 6 cubic decimeter per sqm including preparation of surface, excluding grading, compete — is derived from 9 priced inputs for 30 sqm and works out to ₹910.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Blown bitumen applied hot
  • (1.45+1.20+1.70)x30 = 131 kg.
  • Bitumen felt type B grade I (fibre base self
  • finished bitumen felt) = 60 sqm. + Add for over
  • lapping @ 10% = 6 sqm. Total =66 Sqm
  • 30x6=180cudm
  • CARRIAGE:
  • Fuel (Steam coal) = 2 quintals/t of bitumen i.e.
  • 2x0.131=0.262q
CodeInputUnitQuantityRate (INR)Amount (INR)
0313Blown type petroleum bitumen of penetration 85/25 of approved qualityMaterialtonne0.13138,250.005,010.75
0318Bitumen felt fibre base (vegetable or animal):- Type 2 grade 1Bitumen felt fibre base (vegetable or animal):As per IS 7193 Grade IMaterialsqm6675.004,950.00
1177Stone grit 6 mm and down size or pea sized gravelMaterialcum0.18985.00177.30
0370Coal (steam)Materialquintal0.262500.00131.00
9999Praparing roof surface, sutting groove and making good etcMaterialL.S.134.552.27305.43
0131PainterLabourday4.32816.003,525.12
0114BeldarLabourday6.48736.004,769.28
0130MistryLabourday0.36897.00322.92
9999Sundries, brushes etc.MaterialL.S.6.762.2715.35
TOTAL
19,207.15
Add 1 % Water charges on “W”
192.07
TOTAL
19,399.22
Add GST on “X” (multiplying factor 0.2127)
4,126.21
TOTAL
23,525.43
Add 15% CPOH on “Y”
3,528.81
TOTAL
27,054.24
Add Cess @ 1% on “Z”
270.54
Cost of 30.00 Sqm.
27,324.78
Cost of 1.00 Sqm.
910.83
Say
910.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1854. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.