Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not exceeding 6 m
- Item number
- 7.18
- Analysis basis
- 10 cudm
- Priced inputs
- 1
- Derived rate
- ₹2,014.00/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.18 (Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not exceeding 6 m) is derived from 1 priced inputs for 10 cudm and works out to ₹2,014.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 9999 | MAT | Labour and materials | L.S. | 6.24 | 2.27 | 14.16 |
- TOTAL
- 14.16
- Add 1 % Water charges on “W”
- +0.14
- TOTAL
- 14.30
- Add GST on “X” (multiplying factor 0.2127)
- +3.04
- TOTAL
- 17.34
- Add 15% CPOH on “Y”
- +2.60
- TOTAL
- 19.94
- Add Cess @ 1% on “Z”
- +0.20
- Cost of 10 cudm.
- 20.14
- Cost of 1 cum.
- 2,014.00
- SAY
- ₹2,014.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 365
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 365. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.