Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not exceeding 6 m

Item number
7.18
Analysis basis
10 cudm
Priced inputs
1
Derived rate
₹2,014.00/ CUM
D-01/RATE ANALYSISITEM 7.18

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.18 (Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean radius not exceeding 6 m) is derived from 1 priced inputs for 10 cudm and works out to ₹2,014.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 7.18DETAILS OF COST FOR 10 CUDM OR 0.01 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
9999MATLabour and materialsL.S.6.242.2714.16
BUILD-UP TO RATE
TOTAL
14.16
Add 1 % Water charges on “W”
+0.14
TOTAL
14.30
Add GST on “X” (multiplying factor 0.2127)
+3.04
TOTAL
17.34
Add 15% CPOH on “Y”
+2.60
TOTAL
19.94
Add Cess @ 1% on “Z”
+0.20
Cost of 10 cudm.
20.14
Cost of 1 cum.
2,014.00
SAY
₹2,014.00
D-02/SOURCEPRINTED PAGE 365
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
365

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 365. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.