Stone work plain ashlar in domes , in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade One face dressed
- Item number
- 7.14.1.1
- Analysis basis
- 10 cudm
- Priced inputs
- 18
- Derived rate
- ₹1,14,277.00/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.14.1.1 (Stone work plain ashlar in domes , in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade One face dressed Red sand stone) is derived from 18 priced inputs for 10 cudm and works out to ₹1,14,277.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 cudm. Add wastage
- @ 33.3% = 3.33 cudm. Total = 13.33
- cudm.
- Fixing charges
- Extra labour for lifting of material up to
- floor five level (0.01 x 1.5 = 0.015)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1160 | MAT | Red sand stone block | 10 cudm | 1.333 | 130.00 | 173.29 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.176 | 816.00 | 143.62 |
| 0102 | LAB | Blacksmith 1st class | day | 0.006 | 897.00 | 5.38 |
| 0126 | LAB | Mason (for ornamental stone work) 1st class | day | 0.176 | 897.00 | 157.87 |
| 0114 | LAB | Beldar | day | 0.044 | 736.00 | 32.38 |
| 0115 | LAB | Coolie | day | 0.022 | 736.00 | 16.19 |
| 0100 | LAB | Bandhani | day | 0.044 | 816.00 | 35.90 |
| 0125 | LAB | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd class | day | 0.044 | 816.00 | 35.90 |
| 0102 | LAB | Blacksmith 1st class | day | 0.006 | 897.00 | 5.38 |
| 0114 | LAB | Beldar | day | 0.022 | 736.00 | 16.19 |
| 0115 | LAB | Coolie | day | 0.022 | 736.00 | 16.19 |
| 0100 | LAB | Bandhani | day | 0.022 | 816.00 | 17.95 |
| 0101 | LAB | Bhisti | day | 0.022 | 816.00 | 17.95 |
| 9999 | MAT | Scaffolding | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Mortar for laying and pointing | L.S. | 8.06 | 2.27 | 18.30 |
| 9999 | MAT | Centring and shuttering | L.S. | 33.15 | 2.27 | 75.25 |
| 9999 | MAT | Extra for using white cement | L.S. | 8.06 | 2.27 | 18.30 |
| 0115 | LAB | Coolie | day | 0.015 | 736.00 | 11.04 |
- TOTAL
- 803.28
- Add 1 % Water charges on “W”
- +8.03
- TOTAL
- 811.31
- Add GST on “X” (multiplying factor 0.2127)
- +172.57
- TOTAL
- 983.88
- Add 15% CPOH on “Y”
- +147.58
- TOTAL
- 1,131.46
- Add Cess @ 1% on “Z”
- +11.31
- Cost of 10 cudm.
- 1,142.77
- Cost of 1 cum.
- 1,14,277.00
- SAY
- ₹1,14,277.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 357
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 357. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.