CPWD Analysis of Rates · Stone Work
Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar Both face dressed
Red sand stone
- Item number
- 7.13.2.1
- Analysis basis
- Details of cost for 10 cudm or 0.01 cum
- Priced inputs
- 17
- Derived rate
- ₹98,265.00 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.13.2.1 — Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar Both face dressed Red sand stone — is derived from 17 priced inputs for 10 cudm and works out to ₹98,265.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Finished work = 10 cudm.+ Add wastage
- @ 33.3% = 3.33 cudm. Total = 13.33
- cudm.
- Dressing charges
- Fixing charges
- Extra labour for lifting of material (above
- floor two level up to floor five level) (0.01
- x 1.5 = 0.015)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1160 | Red sand stone blockMaterial | 10 cudm | 1.333 | 130.00 | 173.29 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.176 | 816.00 | 143.62 |
| 0102 | Blacksmith 1st classLabour | day | 0.012 | 897.00 | 10.76 |
| 0114 | BeldarLabour | day | 0.088 | 736.00 | 64.77 |
| 0115 | CoolieLabour | day | 0.044 | 736.00 | 32.38 |
| 0100 | BandhaniLabour | day | 0.088 | 816.00 | 71.81 |
| 0125 | Mason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classLabour | day | 0.044 | 816.00 | 35.90 |
| 0102 | Blacksmith 1st classLabour | day | 0.006 | 897.00 | 5.38 |
| 0114 | BeldarLabour | day | 0.022 | 736.00 | 16.19 |
| 0115 | CoolieLabour | day | 0.022 | 736.00 | 16.19 |
| 0100 | BandhaniLabour | day | 0.022 | 816.00 | 17.95 |
| 0101 | BhistiLabour | day | 0.022 | 816.00 | 17.95 |
| 9999 | ScaffoldingMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | Mortar for laying and pointingMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 9999 | Centering and shutteringMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Extra for using white cementMaterial | L.S. | 8.06 | 2.27 | 18.30 |
| 0115 | CoolieLabour | day | 0.015 | 736.00 | 11.04 |
- TOTAL
- 690.72
- Add 1 % Water charges on “W”
- 6.91
- TOTAL
- 697.63
- Add GST on “X” (multiplying factor 0.2127)
- 148.39
- TOTAL
- 846.02
- Add 15% CPOH on “Y”
- 126.90
- TOTAL
- 972.92
- Add Cess @ 1% on “Z”
- 9.73
- Cost of 10 cudm.
- 982.65
- Cost of 1 cum.
- 98,265.00
- Say
- 98,265.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 356. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.