Skip to main content
R/DAR 2023

Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar Both face dressed

Red sand stone
Item number
7.13.2.1
Analysis basis
10 cudm
Priced inputs
17
Derived rate
₹98,265.00/ CUM
D-01/RATE ANALYSISITEM 7.13.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 7.13.2.1 (Stone work plain ashlar in arches in super structure upto floor V level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering, shuttering and pointing with white cement mortar Both face dressed Red sand stone) is derived from 17 priced inputs for 10 cudm and works out to ₹98,265.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Finished work = 10 cudm.+ Add wastage
  • @ 33.3% = 3.33 cudm. Total = 13.33
  • cudm.
  • Dressing charges
  • Fixing charges
  • Extra labour for lifting of material (above
  • floor two level up to floor five level) (0.01
  • x 1.5 = 0.015)
ANALYSIS OF RATES · ITEM 7.13.2.1DETAILS OF COST FOR 10 CUDM OR 0.01 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1160MATRed sand stone block10 cudm1.333130.00173.29
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.176816.00143.62
0102LABBlacksmith 1st classday0.012897.0010.76
0114LABBeldarday0.088736.0064.77
0115LABCoolieday0.044736.0032.38
0100LABBandhaniday0.088816.0071.81
0125LABMason (for plain stone work) 2nd class)Mason (for plain stone work) 2nd classday0.044816.0035.90
0102LABBlacksmith 1st classday0.006897.005.38
0114LABBeldarday0.022736.0016.19
0115LABCoolieday0.022736.0016.19
0100LABBandhaniday0.022816.0017.95
0101LABBhistiday0.022816.0017.95
9999MATScaffoldingL.S.2.732.276.20
9999MATMortar for laying and pointingL.S.8.062.2718.30
9999MATCentering and shutteringL.S.13.522.2730.69
9999MATExtra for using white cementL.S.8.062.2718.30
0115LABCoolieday0.015736.0011.04
BUILD-UP TO RATE
TOTAL
690.72
Add 1 % Water charges on “W”
+6.91
TOTAL
697.63
Add GST on “X” (multiplying factor 0.2127)
+148.39
TOTAL
846.02
Add 15% CPOH on “Y”
+126.90
TOTAL
972.92
Add Cess @ 1% on “Z”
+9.73
Cost of 10 cudm.
982.65
Cost of 1 cum.
98,265.00
SAY
₹98,265.00
D-02/SOURCEPRINTED PAGE 356
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
356

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 356. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTONE WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.