CPWD Analysis of Rates · Steel Work

Providing and fixing carbon steel galvanised ( minimum coating 5 micron) dash fastener of 10 mm dia double threaded 6.8 grade (yield strength 480 N/mm2), counter sunk head, comprising of 10 mm dia polyamide PA 6 grade sleeve, including drilling of hole in frame , concrete/ masonry, etc. as per direction of Engineer-in-charge

10 x 80 mm

Item number
10.27.2
Analysis basis
Details of cost for 10 nos.
Priced inputs
4
Derived rate
137.65 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.27.2 Providing and fixing carbon steel galvanised ( minimum coating 5 micron) dash fastener of 10 mm dia double threaded 6.8 grade (yield strength 480 N/mm2), counter sunk head, comprising of 10 mm dia polyamide PA 6 grade sleeve, including drilling of hole in frame , concrete/ masonry, etc. as per direction of Engineer-in-charge 10 x 80 mm — is derived from 4 priced inputs for 10 nos and works out to ₹137.65 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
2507Carben Steel galvanised dash fastner (min5 micron) of 10 mm dia double threaded 6.8 grade counter sunk head screw comprising of 10 mm dia polyamide PA 6 grade sleave. Size 10mm x 80mmCarben Steel galvanised (min 5 micron) dash fastner (min 5 micron) of 10 mm dia double threaded 6.8 grade counter sunk head screw comprising of 10 mm dia polyamide PA 6 grade sleeve. Size 10 mm x 80 mmMaterial10 nos1324.00324.00
0124Mason 2nd classMason 2nd classLabourday0.4816.00326.40
0114BeldarLabourday0.4736.00294.40
9977Sundries for carriage of materialMaterialL.S.102.2722.70
TOTAL
967.50
Add 1 % Water charges on “W”
9.68
TOTAL
977.18
Add GST on “X” (multiplying factor 0.2127)
207.85
TOTAL
1,185.03
Add 15% CPOH on “Y”
177.75
TOTAL
1,362.78
Add Cess @ 1% on “Z”
13.63
Cost of 10 Nos.
1,376.41
Cost of 1 no
137.64
Say
137.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 746. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.