Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete

Item number
10.1
Analysis basis
one qunital
Priced inputs
6
Derived rate
₹117.35/ KG
D-01/RATE ANALYSISITEM 10.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.1 (Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete) is derived from 6 priced inputs for one qunital and works out to ₹117.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Steel = 1.00q
  • Total = 1.05q
  • Priming Coat
  • Add wastage @ 5% = 0.05q
ANALYSIS OF RATES · ITEM 10.1DETAILS OF COST FOR ONE QUNITAL
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal1.055,965.006,263.25
0116LABFitter (grade 1)day0.5897.00448.50
0103LABBlacksmith 2nd classday0.75816.00612.00
0114LABBeldarday1736.00736.00
SUBRate as per Item Number 13.50.3 of SH:FinishingRate as per item 13.50.3sqm367.40202.20
9999MATSundriesL.S.20.672.2746.92
BUILD-UP TO RATE
TOTAL
8,308.87
Add 1 % Water charges on “W-A”
+81.07
TOTAL
8,389.94
Add GST on “X-A” (multiplying factor 0.2127)
+1,741.53
TOTAL
10,131.47
Add 15% CPOH on “Y-A”
+1,489.39
TOTAL
11,620.86
Add Cess @ 1% on “Z-A”
+114.19
Cost of 1qunital
11,735.05
Cost of 1 Kg.
117.35
SAY
₹117.35
D-02/SOURCEPRINTED PAGE 713
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
713

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 713. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSTEEL WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.