Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete
- Item number
- 10.1
- Analysis basis
- one qunital
- Priced inputs
- 6
- Derived rate
- ₹117.35/ KG
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.1 (Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete) is derived from 6 priced inputs for one qunital and works out to ₹117.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- Steel = 1.00q
- Total = 1.05q
- Priming Coat
- Add wastage @ 5% = 0.05q
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1007 | MAT | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joists | quintal | 1.05 | 5,965.00 | 6,263.25 |
| 0116 | LAB | Fitter (grade 1) | day | 0.5 | 897.00 | 448.50 |
| 0103 | LAB | Blacksmith 2nd class | day | 0.75 | 816.00 | 612.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| SUB | Rate as per Item Number 13.50.3 of SH:FinishingRate as per item 13.50.3 | sqm | 3 | 67.40 | 202.20 | |
| 9999 | MAT | Sundries | L.S. | 20.67 | 2.27 | 46.92 |
- TOTAL
- 8,308.87
- Add 1 % Water charges on “W-A”
- +81.07
- TOTAL
- 8,389.94
- Add GST on “X-A” (multiplying factor 0.2127)
- +1,741.53
- TOTAL
- 10,131.47
- Add 15% CPOH on “Y-A”
- +1,489.39
- TOTAL
- 11,620.86
- Add Cess @ 1% on “Z-A”
- +114.19
- Cost of 1qunital
- 11,735.05
- Cost of 1 Kg.
- 117.35
- SAY
- ₹117.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 713
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 713. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.