CPWD Analysis of Rates · Steel Work

Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete

Item number
10.1
Analysis basis
Details of cost for one qunital
Priced inputs
6
Derived rate
117.35 / Kg

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 10.1 Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete — is derived from 6 priced inputs for one qunital and works out to ₹117.35 per kg after water charges, GST, CPOH and cess. The full build-up is below.

  • Steel = 1.00q
  • Total = 1.05q
  • Priming Coat
  • Add wastage @ 5% = 0.05q
CodeInputUnitQuantityRate (INR)Amount (INR)
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal1.055,965.006,263.25
0116Fitter (grade 1)Labourday0.5897.00448.50
0103Blacksmith 2nd classLabourday0.75816.00612.00
0114BeldarLabourday1736.00736.00
Rate as per Item Number 13.50.3 of SH:FinishingRate as per item 13.50.3Sub-analysissqm367.40202.20
9999SundriesMaterialL.S.20.672.2746.92
TOTAL
8,308.87
Add 1 % Water charges on “W-A”
81.07
TOTAL
8,389.94
Add GST on “X-A” (multiplying factor 0.2127)
1,741.53
TOTAL
10,131.47
Add 15% CPOH on “Y-A”
1,489.39
TOTAL
11,620.86
Add Cess @ 1% on “Z-A”
114.19
Cost of 1qunital
11,735.05
Cost of 1 Kg.
117.35
Say
117.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 713. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.