R/DAR 2023

Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of M.S. flat brackets made of 50x5 mm flat of specified shape, projecting 75 mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion hold fasteners, including drilling necessary holes in brick wall/ CC/ RCC surface and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30 mm x1.6 mm galvanised M.S. flats of specified shape and of total length 420 mm and shall be fixed with M.S. nuts, bolts, & washers of size 25x6 mm, one bolts on each side of the pipe

Total bracket length 810 mm of approved shape and design (for two 100 mm dia pipes)
Item number
17.77.2
Analysis basis
50 nos
Priced inputs
7
Derived rate
₹378.10/ NOS
D-01/RATE ANALYSISITEM 17.77.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.77.2 (Providing and fixing M.S. holder bat clamp of approved design to sand cast iron/ cast iron (spun) pipes comprising of M.S. flat brackets made of 50x5 mm flat of specified shape, projecting 75 mm outside the wall surface and fixed on wall with 4nos, 6mm dia expansion hold fasteners, including drilling necessary holes in brick wall/ CC/ RCC surface and the cost of bolts etc. The pipes shall be fixed to the already fixed brackets with the help of 30 mm x1.6 mm galvanised M.S. flats of specified shape and of total length 420 mm and shall be fixed with M.S. nuts, bolts, & washers of size 25x6 mm, one bolts on each side of the pipe Total bracket length 810 mm of approved shape and design (for two 100 mm dia pipes)) is derived from 7 priced inputs for 50 nos and works out to ₹378.10 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • M.S. flats 50x5mm= 50 x 0.81 = 40.5m
  • @ 1.97 kg/ metre = 79.8 kg.
  • M.S. flats 30x1.6mm =50x2x0.42 = 42m.
  • 0.38kg/metre = 16kg.
  • Total = 95.8kg.
  • Total = 100.6 kg.
  • M.S.flats= 100.6kg. = 1.006 quintal
  • priming coat
  • 50x0.81x0.11 = 4.46
  • 50x2x0.42x0.063 = 2.65
  • Total =7.11sqm
  • P/F expansion hold fasteners 6mm
  • threaded dia = 50x4 Nos = 200 nos.
  • Add wastage 5% = 4.8kg.
ANALYSIS OF RATES · ITEM 17.77.2DETAILS OF COST FOR 50 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1007MATStructurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsquintal1.0065,965.006,000.79
0116LABFitter (grade 1)day0.48897.00430.56
0103LABBlacksmith 2nd classday0.72816.00587.52
0114LABBeldarday0.96736.00706.56
SUBRate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1sqm7.1170.35500.19
9999MATSundriesL.S.19.82.2744.95
SUBRate asper item no. 8.8.1.1 of SH :- Marble workRate as per item 8.8.1.1each20036.757,350.00
BUILD-UP TO RATE
TOTAL
15,620.57
Add 1 % Water charges on “W-A”
+77.70
TOTAL
15,698.27
Add GST on “X-A” (multiplying factor 0.2127)
+1,669.29
TOTAL
17,367.56
Add 15% CPOH on “Y-A”
+1,427.61
TOTAL
18,795.17
Add Cess @ 1% on “Z-A”
+109.45
Cost of 50 Nos.
18,904.62
Cost of each
378.09
SAY
₹378.10
D-02/SOURCEPRINTED PAGE 1387
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1387

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1387. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.