Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require
- Item number
- 17.7.5
- Analysis basis
- one no
- Priced inputs
- 9
- Derived rate
- ₹2,226.35/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.7.5 (Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: White Vitreous China Angle back wash basin size 600 x 480 mm with single 15mm C.P. brass pillar tap) is derived from 9 priced inputs for one no and works out to ₹2,226.35 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1949 | MAT | Vitreous china angle back wash basin 600x480 mm | each | 1 | 798.00 | 798.00 |
| 1885 | MAT | 15 mm C.P.brass tap15 mm C.P. brass tap | each | 1 | 297.00 | 297.00 |
| 1951 | MAT | C.P. brass waste 32 mm | each | 1 | 94.00 | 94.00 |
| 1309 | MAT | C.I. bracket for wash basin and sinks | pair | 1 | 95.00 | 95.00 |
| 9999 | MAT | Red lead, white lead and gaskit | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | MAT | Cement, sand and grit etc. | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | MAT | Painting of brackets, fittings etc. | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | MAT | Carriage of materials | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | MAT | Fixing Charges | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 1,564.94
- Add 1 % Water charges on “W”
- +15.65
- TOTAL
- 1,580.59
- Add GST on “X” (multiplying factor 0.2127)
- +336.19
- TOTAL
- 1,916.78
- Add 15% CPOH on “Y”
- +287.52
- TOTAL
- 2,204.30
- Add Cess @ 1% on “Z”
- +22.04
- Cost of each
- 2,226.34
- SAY
- ₹2,226.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1295
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1295. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.