CPWD Analysis of Rates · Sanitary Installations
Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require
White Vitreous China Wash basin size 630x450 mm with a single 15 mm C.P. brass pillar tap
- Item number
- 17.7.2
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 9
- Derived rate
- ₹2,226.35 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.7.2 — Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps, 32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require: White Vitreous China Wash basin size 630x450 mm with a single 15 mm C.P. brass pillar tap — is derived from 9 priced inputs for one no and works out to ₹2,226.35 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1947 | Vitreous china flat back wash basin 630x450 mmMaterial | each | 1 | 798.00 | 798.00 |
| 1885 | 15 mm C.P.brass tap15 mm C.P. brass tapMaterial | each | 1 | 297.00 | 297.00 |
| 1951 | C.P. brass waste 32 mmMaterial | each | 1 | 94.00 | 94.00 |
| 1309 | C.I. bracket for wash basin and sinksMaterial | pair | 1 | 95.00 | 95.00 |
| 9999 | Red lead, white lead and gaskitMaterial | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 13.39 | 2.27 | 30.40 |
| 9999 | Painting of brackets, fittings etc.Material | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | Carriage of materialsMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Fixing ChargesMaterial | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 1,564.94
- Add 1 % Water charges on “W”
- 15.65
- TOTAL
- 1,580.59
- Add GST on “X” (multiplying factor 0.2127)
- 336.19
- TOTAL
- 1,916.78
- Add 15% CPOH on “Y”
- 287.52
- TOTAL
- 2,204.30
- Add Cess @ 1% on “Z”
- 22.04
- Cost of each
- 2,226.34
- Say
- 2,226.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1293. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.