Skip to main content
R/DAR 2023

Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with one coat of synthetic enamel paint of any colour such as chocolate, grey or buff etc

75 mm diameter pipe
Item number
17.66.2
Analysis basis
10 metres
Priced inputs
2
Derived rate
₹29.55/ METRE
D-01/RATE ANALYSISITEM 17.66.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.66.2 (Repainting sand cast iron/ centrifugally cast iron (spun) iron, soil, waste, vent pipes and fittings with one coat of synthetic enamel paint of any colour such as chocolate, grey or buff etc : 75 mm diameter pipe) is derived from 2 priced inputs for 10 metres and works out to ₹29.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Painting one coat with paint of any colour
  • such as chocolate,grey or buff etc.
ANALYSIS OF RATES · ITEM 17.66.2DETAILS OF COST FOR 10 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUB(Rate as per item no 13.99.1 of S.H. Finishing)Rate as per item 13.99.1sqm2.577102.80264.92
9999MATAdd for delayL.S.9.492.2721.54
BUILD-UP TO RATE
TOTAL
286.46
Add 1 % Water charges on “W-A”
+0.22
TOTAL
286.68
Add GST on “X-A” (multiplying factor 0.2127)
+4.63
TOTAL
291.31
Add 15% CPOH on “Y-A”
+3.96
TOTAL
295.27
Add Cess @ 1% on “Z-A”
+0.30
Cost of 10 metres
295.57
Cost of 1 metre
29.56
SAY
₹29.55
D-02/SOURCEPRINTED PAGE 1379
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1379

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1379. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.