Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 100 mm outlet

Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905
Item number
17.60.1.3
Analysis basis
one no
Priced inputs
2
Derived rate
₹854.55/ ONE NO
D-01/RATE ANALYSISITEM 17.60.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.60.1.3 (Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 100 mm outlet Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905) is derived from 2 priced inputs for one no and works out to ₹854.55 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.60.1.3DETAIL OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7642MATHubless centrifugally cast (spun) iron trap with 100 mm inlet and 100 mm outlet as per IS 15905Hubless centrifugally cast (spun) iron trap with 100 mm inlet and 100 mm outlet as per IS 15905each1570.00570.00
9977MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
600.69
Add 1 % Water charges on “W”
+6.01
TOTAL
606.70
Add GST on “X” (multiplying factor 0.2127)
+129.05
TOTAL
735.75
Add 15% CPOH on “Y”
+110.36
TOTAL
846.11
Add Cess @ 1% on “Z”
+8.46
Cost of each
854.57
SAY
₹854.55
D-02/SOURCEPRINTED PAGE 1373
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1373

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1373. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.