Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 100 mm outlet

Sand cast iron S&S as per IS: 3989
Item number
17.60.1.1
Analysis basis
one no
Priced inputs
5
Derived rate
₹1,996.50/ ONE NO
D-01/RATE ANALYSISITEM 17.60.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.60.1.1 (Providing and fixing trap of self cleansing design with screwed down or hinged grating with or without vent arm complete, including cost of cutting and making good the walls and floors : 100 mm inlet and 100 mm outlet Sand cast iron S&S as per IS: 3989) is derived from 5 priced inputs for one no and works out to ₹1,996.50 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.60.1.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7808MATCentrifugally cast (spun) iron S&S 100 mm inlet and 100 mm outlet trapeach1550.00550.00
9999MATCement, sand and grit etc.L.S.13.522.2730.69
9977MATCarriage of materialsL.S.2.732.276.20
0123LABMason 1st classMason 1st classday0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
1,403.39
Add 1 % Water charges on “W”
+14.03
TOTAL
1,417.42
Add GST on “X” (multiplying factor 0.2127)
+301.49
TOTAL
1,718.91
Add 15% CPOH on “Y”
+257.84
TOTAL
1,976.75
Add Cess @ 1% on “Z”
+19.77
Cost of each
1,996.52
SAY
₹1,996.50
D-02/SOURCEPRINTED PAGE 1372
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1372

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1372. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.