CPWD Analysis of Rates · Sanitary Installations
Providing lead caulked joints to sand cast iron/centrifugally cast (spun) iron pipes and fittings of diameter
50 mm
- Item number
- 17.58.3
- Analysis basis
- Details of cost for one joint
- Priced inputs
- 7
- Derived rate
- ₹423.15 / one joint
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.58.3 — Providing lead caulked joints to sand cast iron/centrifugally cast (spun) iron pipes and fittings of diameter : 50 mm — is derived from 7 priced inputs for one joint and works out to ₹423.15 per one joint after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1397 | Pig leadMaterial | kilogram | 0.77 | 210.00 | 161.70 |
| 1881 | Spun yarnMaterial | kilogram | 0.06 | 61.00 | 3.66 |
| 9999 | Kerosene oil, fuel and other sundriesMaterial | L.S. | 6.76 | 2.27 | 15.35 |
| 9977 | Carriage of materialsMaterial | L.S. | 1.43 | 2.27 | 3.25 |
| 0116 | Fitter (grade 1)Labour | day | 0.04 | 897.00 | 35.88 |
| 0117 | Assistant Fitter or 2nd class FitterLabour | day | 0.05 | 816.00 | 40.80 |
| 0114 | BeldarLabour | day | 0.05 | 736.00 | 36.80 |
- TOTAL
- 297.44
- Add 1 % Water charges on “W”
- 2.97
- TOTAL
- 300.41
- Add GST on “X” (multiplying factor 0.2127)
- 63.90
- TOTAL
- 364.31
- Add 15% CPOH on “Y”
- 54.65
- TOTAL
- 418.96
- Add Cess @ 1% on “Z”
- 4.19
- Cost of each
- 423.15
- Say
- 423.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1370. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works