Providing and fixing single equal plain invert branch of required degree : 75x75x75 mm

Sand cast iron S&S as per IS - 3989
Item number
17.50.2.2
Analysis basis
one no
Priced inputs
2
Derived rate
₹575.45/ ONE NO
D-01/RATE ANALYSISITEM 17.50.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.50.2.2 (Providing and fixing single equal plain invert branch of required degree : 75x75x75 mm Sand cast iron S&S as per IS - 3989) is derived from 2 priced inputs for one no and works out to ₹575.45 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.50.2.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3682MATS.C.I. S&S single equal invert branch of required degree 75x75x75 mm diaS.C.I. S&S single equal invert branch of required degree 75x75x 75 mm diaeach1380.00380.00
9988MATCarriage of materials and fixing chargesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
404.49
Add 1 % Water charges on “W”
+4.04
TOTAL
408.53
Add GST on “X” (multiplying factor 0.2127)
+86.89
TOTAL
495.42
Add 15% CPOH on “Y”
+74.31
TOTAL
569.73
Add Cess @ 1% on “Z”
+5.70
Cost of each
575.43
SAY
₹575.45
D-02/SOURCEPRINTED PAGE 1355
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1355

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1355. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.