CPWD Analysis of Rates · Sanitary Installations
Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350 mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including painting of fittings and cutting and making good the walls and floors wherever required
Range of two half stall urinals with 5 litre P.V.C. automatic flushing cistern
- Item number
- 17.5.2
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 11
- Derived rate
- ₹18,008.75 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.5.2 — Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350 mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass, including painting of fittings and cutting and making good the walls and floors wherever required: Range of two half stall urinals with 5 litre P.V.C. automatic flushing cistern — is derived from 11 priced inputs for one no and works out to ₹18,008.75 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7379 | White vitreous china clay half stall urinal flat back 580x380x350 mm or angle back 450x375x350 mm with waste fittings as per IS : 2556White vitreous china clay half stall urinal flat back 580x380x350 mm or angle back 450x375x350 mm with waste fittings as per IS:2556Material | each | 2 | 915.00 | 1,830.00 |
| 7359 | P.V.C. automatic flushing cistern 5 lts capacityP.V.C. automatic flushing cistern 5 litre capacityMaterial | each | 1 | 477.00 | 477.00 |
| 1533 | Flush pipe with union spreaders and clamps all in C.P. brass for double stallMaterial | each | 1 | 450.00 | 450.00 |
| 1891 | C.I. trap for standard urinal with vent arm with operating and other couplings in C.P.brass: 50 mm diaC.I. trap for standard urinal with vent arm with operating and other couplings in C.P. brass: 50 mm diaMaterial | each | 1 | 209.00 | 209.00 |
| 9999 | Red lead, white lead and gaskitMaterial | L.S. | 17.55 | 2.27 | 39.84 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 53.82 | 2.27 | 122.17 |
| 9999 | Painting of fittings etc.Material | L.S. | 26 | 2.27 | 59.02 |
| 9977 | Carriage of materialsMaterial | L.S. | 53.82 | 2.27 | 122.17 |
| 0116 | Fitter (grade 1)Labour | day | 2.5 | 897.00 | 2,242.50 |
| 0123 | Mason 1st classMason 1st classLabour | day | 3 | 897.00 | 2,691.00 |
| 0114 | BeldarLabour | day | 6 | 736.00 | 4,416.00 |
- TOTAL
- 12,658.70
- Add 1 % Water charges on “W”
- 126.59
- TOTAL
- 12,785.29
- Add GST on “X” (multiplying factor 0.2127)
- 2,719.43
- TOTAL
- 15,504.72
- Add 15% CPOH on “Y”
- 2,325.71
- TOTAL
- 17,830.43
- Add Cess @ 1% on “Z”
- 178.30
- Cost of each
- 18,008.73
- Say
- 18,008.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1288. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works