Providing and fixing double unequal plain junction of required degree : 100x100x75x75 mm

Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905
Item number
17.46.1.3
Analysis basis
one no
Priced inputs
2
Derived rate
₹607.05/ ONE NO
D-01/RATE ANALYSISITEM 17.46.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.46.1.3 (Providing and fixing double unequal plain junction of required degree : 100x100x75x75 mm Hubless centrifugally cast (spun) iron epoxy coated inside & outside as per IS:15905) is derived from 2 priced inputs for one no and works out to ₹607.05 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.46.1.3DETAIL OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7629MATHubless centrifugally cast (spun) iron double unequal plain junction as per IS 15905 - 100x100x75x75 mm diaeach1396.00396.00
9977MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
426.69
Add 1 % Water charges on “W”
+4.27
TOTAL
430.96
Add GST on “X” (multiplying factor 0.2127)
+91.67
TOTAL
522.63
Add 15% CPOH on “Y”
+78.39
TOTAL
601.02
Add Cess @ 1% on “Z”
+6.01
Cost of each
607.03
SAY
₹607.05
D-02/SOURCEPRINTED PAGE 1349
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1349

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1349. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.