Providing and fixing double unequal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete: 100x100x75x75 mm

Sand cast iron S&S as per IS - 1729
Item number
17.45.1.1
Analysis basis
one no
Priced inputs
3
Derived rate
₹1,153.30/ ONE NO
D-01/RATE ANALYSISITEM 17.45.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.45.1.1 (Providing and fixing double unequal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete: 100x100x75x75 mm Sand cast iron S&S as per IS - 1729) is derived from 3 priced inputs for one no and works out to ₹1,153.30 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.45.1.1DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1662MATSand cast iron S&S double unequal junctions: 100x100x75x75 mm dia with access dooreach1760.00760.00
1374MATRubber insertions for 100 mm dia pipe jointseach120.0020.00
9988MATCarriage of materials and fixing chargesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
810.69
Add 1 % Water charges on “W”
+8.11
TOTAL
818.80
Add GST on “X” (multiplying factor 0.2127)
+174.16
TOTAL
992.96
Add 15% CPOH on “Y”
+148.94
TOTAL
1,141.90
Add Cess @ 1% on “Z”
+11.42
Cost of each
1,153.32
SAY
₹1,153.30
D-02/SOURCEPRINTED PAGE 1347
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1347

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1347. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.