Providing and fixing double equal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete : 75x75x75x75 mm

Sand cast iron S&S as per IS - 3989
Item number
17.41.2.2
Analysis basis
one no
Priced inputs
3
Derived rate
₹885.60/ ONE NO
D-01/RATE ANALYSISITEM 17.41.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.41.2.2 (Providing and fixing double equal junction of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete : 75x75x75x75 mm Sand cast iron S&S as per IS - 3989) is derived from 3 priced inputs for one no and works out to ₹885.60 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.41.2.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3655MATS.C.I. S&S double equal junctions with access door 75x75x75x75 mmeach1580.00580.00
1373MATRubber insertions for 80 mm dia pipe jointsRubber insertions for 75 mm dia pipe jointseach118.0018.00
9988MATCarriage of materials and fixing chargesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
622.49
Add 1 % Water charges on “W”
+6.22
TOTAL
628.71
Add GST on “X” (multiplying factor 0.2127)
+133.73
TOTAL
762.44
Add 15% CPOH on “Y”
+114.37
TOTAL
876.81
Add Cess @ 1% on “Z”
+8.77
Cost of each
885.58
SAY
₹885.60
D-02/SOURCEPRINTED PAGE 1341
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1341

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1341. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.