CPWD Analysis of Rates · Sanitary Installations
Providing and fixing heel rest sanitary bend 100 mm dia
Sand cast iron S&S as per IS - 1729
- Item number
- 17.40.1.1
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 2
- Derived rate
- ₹584.25 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.40.1.1 — Providing and fixing heel rest sanitary bend 100 mm dia Sand cast iron S&S as per IS - 1729 — is derived from 2 priced inputs for one no and works out to ₹584.25 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1667 | Sand cast iron heel rest bend 100mm diaSand cast iron heel rest bend 100 mm diaMaterial | each | 1 | 380.00 | 380.00 |
| 9988 | Carriage of materials and fixing chargesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 410.69
- Add 1 % Water charges on “W”
- 4.11
- TOTAL
- 414.80
- Add GST on “X” (multiplying factor 0.2127)
- 88.23
- TOTAL
- 503.03
- Add 15% CPOH on “Y”
- 75.45
- TOTAL
- 578.48
- Add Cess @ 1% on “Z”
- 5.78
- Cost of each
- 584.26
- Say
- 584.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1339. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.