Skip to main content

CPWD Analysis of Rates · Sanitary Installations

Providing and fixing plain bend of required degree 100 mm dia

Sand cast iron S&S as per IS - 1729

Item number
17.39.1.1
Analysis basis
Details of cost for one no.
Priced inputs
2
Derived rate
470.45 / one no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.39.1.1 Providing and fixing plain bend of required degree 100 mm dia Sand cast iron S&S as per IS - 1729 — is derived from 2 priced inputs for one no and works out to ₹470.45 per one no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
1621S.C.I. plain bend 100 mm diaMaterialeach1300.00300.00
9988Carriage of materials and fixing chargesMaterialL.S.13.522.2730.69
TOTAL
330.69
Add 1 % Water charges on “W”
3.31
TOTAL
334.00
Add GST on “X” (multiplying factor 0.2127)
71.04
TOTAL
405.04
Add 15% CPOH on “Y”
60.76
TOTAL
465.80
Add Cess @ 1% on “Z”
4.66
Cost of each
470.46
Say
470.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1337. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.