CPWD Analysis of Rates · Sanitary Installations
Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 75 mm dia
Sand cast iron S&S as per IS3989
- Item number
- 17.38.2.2
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 3
- Derived rate
- ₹522.80 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.38.2.2 — Providing and fixing bend of required degree with access door, insertion rubber washer 3 mm thick, bolts and nuts complete 75 mm dia Sand cast iron S&S as per IS3989 — is derived from 3 priced inputs for one no and works out to ₹522.80 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 3625 | S.C.I. S&S bends with access door75mm diaS.C.I. S&S bends with access door 75 mm diaMaterial | each | 1 | 325.00 | 325.00 |
| 1373 | Rubber insertions for 80 mm dia pipe jointsRubber insertions for 75 mm dia pipe jointsMaterial | each | 1 | 18.00 | 18.00 |
| 9988 | Carriage of materials and fixing chargesMaterial | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 367.49
- Add 1 % Water charges on “W”
- 3.67
- TOTAL
- 371.16
- Add GST on “X” (multiplying factor 0.2127)
- 78.95
- TOTAL
- 450.11
- Add 15% CPOH on “Y”
- 67.52
- TOTAL
- 517.63
- Add Cess @ 1% on “Z”
- 5.18
- Cost of each
- 522.81
- Say
- 522.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1336. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.