CPWD Analysis of Rates · Sanitary Installations

Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc.

For 75 mm dia pipe

Item number
17.37.2
Analysis basis
Details of cost for 50 nos.
Priced inputs
19
Derived rate
360.00 / nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.37.2 Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc. : For 75 mm dia pipe — is derived from 19 priced inputs for 50 nos and works out to ₹360.00 each after water charges, GST, CPOH and cess. The full build-up is below.

  • C.C. Black 50x0.1x0.1x0.1 = 0.05 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1332M.S.Holder bat clamp of approved design for75 mm S.C.I. pipeM.S. Holder bat clamp of approved design for 75 mm S.C.I. pipeMaterialeach5025.001,250.00
9977Carriage of bat clampsMaterialL.S.24.72.2756.07
0116Fitter (grade 1)Labourday1.25897.001,121.25
0124Mason 2nd classMason 2nd classLabourday7.5816.006,120.00
0114BeldarLabourday5736.003,680.00
9999SundriesMaterialL.S.71.52.27162.31
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.0331,425.0047.03
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.0111,400.0015.40
0982Coarse sand (zone III)Materialcum0.0221,450.0031.90
0367Portland Cement (OPC-43 grade)Materialtonne0.0165,156.0082.50
0114BeldarLabourday0.045736.0033.12
0115CoolieLabourday0.032736.0023.55
0101BhistiLabourday0.014816.0011.42
0123Mason 1st classMason 1st classLabourday0.003897.002.69
0124Mason 2nd classMason 2nd classLabourday0.003816.002.45
0128MateLabourday0.002816.001.63
9999Hire charges of machine etc.MaterialL.S.2.62.275.90
9999SundriesMaterialL.S.1.32.272.95
9999SundriesMaterialL.S.1.32.272.95
TOTAL
12,653.12
Add 1 % Water charges on “W”
126.53
TOTAL
12,779.65
Add GST on “X” (multiplying factor 0.2127)
2,718.23
TOTAL
15,497.88
Add 15% CPOH on “Y”
2,324.68
TOTAL
17,822.56
Add Cess @ 1% on “Z”
178.23
Cost of 50 bat clamps
18,000.79
Cost of each
360.02
Say
360.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1334. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.