Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc.
- Item number
- 17.37.2
- Analysis basis
- 50 nos
- Priced inputs
- 19
- Derived rate
- ₹360.00/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.37.2 (Providing and fixing M.S. holder-bat clamps of approved design to Sand Cast iron/cast iron (spun) pipe embedded in and including cement concrete blocks 10x10x10 cm of 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size), including cost of cutting holes and making good the walls etc. : For 75 mm dia pipe) is derived from 19 priced inputs for 50 nos and works out to ₹360.00 each after water charges, GST, CPOH and cess. The full build-up is below.
- C.C. Black 50x0.1x0.1x0.1 = 0.05 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1332 | MAT | M.S.Holder bat clamp of approved design for75 mm S.C.I. pipeM.S. Holder bat clamp of approved design for 75 mm S.C.I. pipe | each | 50 | 25.00 | 1,250.00 |
| 9977 | MAT | Carriage of bat clamps | L.S. | 24.7 | 2.27 | 56.07 |
| 0116 | LAB | Fitter (grade 1) | day | 1.25 | 897.00 | 1,121.25 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 7.5 | 816.00 | 6,120.00 |
| 0114 | LAB | Beldar | day | 5 | 736.00 | 3,680.00 |
| 9999 | MAT | Sundries | L.S. | 71.5 | 2.27 | 162.31 |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.033 | 1,425.00 | 47.03 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.011 | 1,400.00 | 15.40 |
| 0982 | MAT | Coarse sand (zone III) | cum | 0.022 | 1,450.00 | 31.90 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.016 | 5,156.00 | 82.50 |
| 0114 | LAB | Beldar | day | 0.045 | 736.00 | 33.12 |
| 0115 | LAB | Coolie | day | 0.032 | 736.00 | 23.55 |
| 0101 | LAB | Bhisti | day | 0.014 | 816.00 | 11.42 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.003 | 897.00 | 2.69 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.003 | 816.00 | 2.45 |
| 0128 | LAB | Mate | day | 0.002 | 816.00 | 1.63 |
| 9999 | MAT | Hire charges of machine etc. | L.S. | 2.6 | 2.27 | 5.90 |
| 9999 | MAT | Sundries | L.S. | 1.3 | 2.27 | 2.95 |
| 9999 | MAT | Sundries | L.S. | 1.3 | 2.27 | 2.95 |
- TOTAL
- 12,653.12
- Add 1 % Water charges on “W”
- +126.53
- TOTAL
- 12,779.65
- Add GST on “X” (multiplying factor 0.2127)
- +2,718.23
- TOTAL
- 15,497.88
- Add 15% CPOH on “Y”
- +2,324.68
- TOTAL
- 17,822.56
- Add Cess @ 1% on “Z”
- +178.23
- Cost of 50 bat clamps
- 18,000.79
- Cost of each
- 360.02
- SAY
- ₹360.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1334
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1334. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.