Providing and fixing white vitreous china wash basin including making all connections but excluding the cost of fittings

Flat back wash basin of size 550x400 mm
Item number
17.25.2
Analysis basis
one no
Priced inputs
3
Derived rate
₹992.60/ ONE NO
D-01/RATE ANALYSISITEM 17.25.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.25.2 (Providing and fixing white vitreous china wash basin including making all connections but excluding the cost of fittings : Flat back wash basin of size 550x400 mm) is derived from 3 priced inputs for one no and works out to ₹992.60 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.25.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3229MATVitreous china flat back wash basin 550x400 mmeach1554.00554.00
9999MATFixing chargesL.S.53.822.27122.17
9977MATCarriage of materialsL.S.9.492.2721.54
BUILD-UP TO RATE
TOTAL
697.71
Add 1 % Water charges on “W”
+6.98
TOTAL
704.69
Add GST on “X” (multiplying factor 0.2127)
+149.89
TOTAL
854.58
Add 15% CPOH on “Y”
+128.19
TOTAL
982.77
Add Cess @ 1% on “Z”
+9.83
Cost of each
992.60
SAY
₹992.60
D-02/SOURCEPRINTED PAGE 1317
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1317

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1317. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.