Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm or 340x410x265 mm sizes respectively
- Item number
- 17.23
- Analysis basis
- one no
- Priced inputs
- 4
- Derived rate
- ₹1,648.95/ ONE NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.23 (Providing and fixing white vitreous china flat back or wall corner type lipped front urinal basin of 430x260x350 mm or 340x410x265 mm sizes respectively) is derived from 4 priced inputs for one no and works out to ₹1,648.95 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1913 | MAT | Vitreous china lipped front urinal | each | 1 | 517.00 | 517.00 |
| 9977 | MAT | Carriage of materials | L.S. | 9.49 | 2.27 | 21.54 |
| 0116 | LAB | Fitter (grade 1) | day | 0.38 | 897.00 | 340.86 |
| 0114 | LAB | Beldar | day | 0.38 | 736.00 | 279.68 |
- TOTAL
- 1,159.08
- Add 1 % Water charges on “W”
- +11.59
- TOTAL
- 1,170.67
- Add GST on “X” (multiplying factor 0.2127)
- +249.00
- TOTAL
- 1,419.67
- Add 15% CPOH on “Y”
- +212.95
- TOTAL
- 1,632.62
- Add Cess @ 1% on “Z”
- +16.33
- Cost of each
- 1,648.95
- SAY
- ₹1,648.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1316
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1316. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.