Skip to main content
R/DAR 2023

Providing and fixing solid plastic seat with lid for pedestal type W.C. pan complete

Black solid plastic seat with lid
Item number
17.20.2
Analysis basis
one no
Priced inputs
2
Derived rate
₹552.55/ ONE NO
D-01/RATE ANALYSISITEM 17.20.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.20.2 (Providing and fixing solid plastic seat with lid for pedestal type W.C. pan complete : Black solid plastic seat with lid) is derived from 2 priced inputs for one no and works out to ₹552.55 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.20.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1876MATBlack plastic seat (solid) with lid C.P.brass hinges and rubber buffersBlack plastic seat (solid) with lid C.P. brass hinges and rubber bufferseach1358.00358.00
9988MATCarriage of materials and fixing chargesL.S.13.392.2730.40
BUILD-UP TO RATE
TOTAL
388.40
Add 1 % Water charges on “W”
+3.88
TOTAL
392.28
Add GST on “X” (multiplying factor 0.2127)
+83.44
TOTAL
475.72
Add 15% CPOH on “Y”
+71.36
TOTAL
547.08
Add Cess @ 1% on “Z”
+5.47
Cost of each
552.55
SAY
₹552.55
D-02/SOURCEPRINTED PAGE 1314
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1314

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1314. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.