Providing and fixing controlled flush, low level cistern made of vitreous china with all fittings complete

10 litre (full flush) capacity-coloured
Item number
17.19.2
Analysis basis
one no
Priced inputs
4
Derived rate
₹2,912.40/ ONE NO
D-01/RATE ANALYSISITEM 17.19.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.19.2 (Providing and fixing controlled flush, low level cistern made of vitreous china with all fittings complete 10 litre (full flush) capacity-coloured) is derived from 4 priced inputs for one no and works out to ₹2,912.40 per one no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 17.19.2DETAILS OF COST FOR ONE NO
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7127MATColoured Vitreous china 10 lit. (full flush) capacity controlled low level flushing cistern with all fittingsColoured Vitreous china 10 litre (full flush) capacity controlled low level flushing cistern with all fittingseach11,200.001,200.00
9977MATCarriage of materialsL.S.13.522.2730.69
0116LABFitter (grade 1)day0.5897.00448.50
0114LABBeldarday0.5736.00368.00
BUILD-UP TO RATE
TOTAL
2,047.19
Add 1 % Water charges on “W”
+20.47
TOTAL
2,067.66
Add GST on “X” (multiplying factor 0.2127)
+439.79
TOTAL
2,507.45
Add 15% CPOH on “Y”
+376.12
TOTAL
2,883.57
Add Cess @ 1% on “Z”
+28.84
Cost of each
2,912.41
SAY
₹2,912.40
D-02/SOURCEPRINTED PAGE 1313
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1313

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1313. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSSANITARY INSTALLATIONS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.