CPWD Analysis of Rates · Sanitary Installations
Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required : Kitchen sink with drain board
510x1040 mm bowl depth 225 mm
- Item number
- 17.10.1.2
- Analysis basis
- Details of cost for one no.
- Priced inputs
- 8
- Derived rate
- ₹7,514.65 / one no
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 17.10.1.2 — Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS:13983 with C.I. brackets and stainless steel plug 40 mm, including painting of fittings and brackets, cutting and making good the walls wherever required : Kitchen sink with drain board 510x1040 mm bowl depth 225 mm — is derived from 8 priced inputs for one no and works out to ₹7,514.65 per one no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7096 | Stainlees steel kitchen sink - with drain board 510 x 1040mm bowl depth 225 mmStainless steel kitchen sink - with drain board 510 x 1040 mm bowl depth 225 mmMaterial | each | 1 | 3,600.00 | 3,600.00 |
| 1309 | C.I. bracket for wash basin and sinksMaterial | pair | 2 | 95.00 | 190.00 |
| 9999 | Cement, sand and grit etc.Material | L.S. | 27.04 | 2.27 | 61.38 |
| 9999 | Painting of brackets etc.Material | L.S. | 26.91 | 2.27 | 61.09 |
| 9977 | Carriage of materialsMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 0116 | Fitter (grade 1)Labour | day | 0.22 | 897.00 | 197.34 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.6 | 897.00 | 538.20 |
| 0114 | BeldarLabour | day | 0.82 | 736.00 | 603.52 |
- TOTAL
- 5,282.22
- Add 1 % Water charges on “W”
- 52.82
- TOTAL
- 5,335.04
- Add GST on “X” (multiplying factor 0.2127)
- 1,134.76
- TOTAL
- 6,469.80
- Add 15% CPOH on “Y”
- 970.47
- TOTAL
- 7,440.27
- Add Cess @ 1% on “Z”
- 74.40
- Cost of each
- 7,514.67
- Say
- 7,514.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1302. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.