CPWD Analysis of Rates · Roofing

Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete

0.80 mm thick with zinc coating not less than 275 gm/m²

Item number
12.7.1
Analysis basis
Details of cost for 90.4m
Priced inputs
15
Derived rate
1,029.65 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.7.1 Providing and fixing 15 cm wide, 45 cm overall semi-circular plain G.S. sheet gutter with iron brackets 40x3mm size, bolts, nuts and washers etc., including making necessary connections with rain water pipes complete 0.80 mm thick with zinc coating not less than 275 gm/m² — is derived from 15 priced inputs and works out to ₹1,029.65 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 0.80mm thick with zinc coating not less than
  • 275gm/m2
  • Consider a length of10x 9.04m =90.4 m
  • Sheet used of size 2.5x0.90m = 2x10 = 20
  • nos.
  • Wt. = 20x15.82=316.4 Kg. = 3.164q
  • Total = 3.164quintal
CodeInputUnitQuantityRate (INR)Amount (INR)
0992Galvanised steel plain sheetsMaterialquintal3.1646,800.0021,515.20
1008Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterialquintal0.7495,450.004,082.05
1022Galvanised steel bolts & nuts 6 mm dia and 25 mmlong round head with slotsGalvanised steel bolts & nuts 6 mm dia and 25 mm long round head with slotsMaterial10 Nos2038.00760.00
1024Galvanised steel bolts & nuts 10 mm dia and 125 mm long round head with slotsMaterialeach3009.002,700.00
1210G.I. plain washer thinMaterial100 Nos721.00147.00
1208Bitumen washerMaterial100 Nos430.00120.00
9977Carriage of G.I. seam bolts and washersMaterialL.S.27.32.2761.97
9999SundriesMaterialL.S.53.32.27120.99
0102Blacksmith 1st classLabourday5897.004,485.00
0114BeldarLabourday5736.003,680.00
9999SundriesMaterialL.S.126.12.27286.25
0130MistryLabourday2.8897.002,511.60
0102Blacksmith 1st classLabourday8.4897.007,534.80
0112Carpenter 2nd classLabourday6.2816.005,059.20
0114BeldarLabourday16.8736.0012,364.80
TOTAL
65,428.86
Add 1 % Water charges on “W”
654.29
TOTAL
66,083.15
Add GST on “X” (multiplying factor 0.2127)
14,055.89
TOTAL
80,139.04
Add 15% CPOH on “Y”
12,020.86
TOTAL
92,159.90
Add Cess @ 1% on “Z”
921.60
Cost of 90.4 metre
93,081.50
Cost of 1.00 metre
1,029.66
Say
1,029.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 861. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.