Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Ridges plain (500600mm)
Item number
12.66.1
Analysis basis
20.20 metre
Priced inputs
6
Derived rate
₹1,066.20/ METRE
D-01/RATE ANALYSISITEM 12.66.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.1 (Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Ridges plain (500600mm)) is derived from 6 priced inputs for 20.20 metre and works out to ₹1,066.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • One piece plain ridges
  • Consider a shed of 20x10m (external dimensions at plinth)
  • Length of ridges 20.2 metre + 5% wastage =
  • 1.01 metre. Total =23.11 metre.
ANALYSIS OF RATES · ITEM 12.66.1DETAIL OF COST FOR 20.20 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3068MATPrecoated/Mill finish Aluminium plain ridges 0.71 mm TCT/plain and 500600 mm widePrecoated/Mill finish Aluminium plain ridges 0.71 mm TCT/plain and 500- 600 mm widemetre23.11576.0013,311.36
9977MATCarriage (The ridge is to be fixed with the same screws as the Sheets)L.S.13.522.2730.69
9999MATSundriesL.S.6.762.2715.35
0130LABMistryday0.14897.00125.58
0112LABCarpenter 2nd classday0.55816.00448.80
0114LABBeldarday1.64736.001,207.04
BUILD-UP TO RATE
Total
15,138.82
Add 1 % Water charges on “W”
+151.39
TOTAL
15,290.21
Add GST on “X” (multiplying factor 0.2127)
+3,252.23
TOTAL
18,542.44
Add 15% CPOH on “Y”
+2,781.37
TOTAL
21,323.81
Add Cess @ 1% on “Z”
+213.24
Cost of 20.20 metre
21,537.05
Cost of 1 metre
1,066.19
SAY
₹1,066.20
D-02/SOURCEPRINTED PAGE 945
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
945

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 945. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.