Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete

Precoated/mill finish aluminium Ridges plain (500600mm)

Item number
12.66.1
Analysis basis
Detail of cost for 20.20 metre
Priced inputs
6
Derived rate
1,066.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.66.1 Providing and fixing of Pre-coated colour or mill finish Aluminium Roofing Accessories in 0.71 mm thickness ,Alloy 31500 (IS designation) [Aluminium Alloy (AA) 3004 (ISO designation)] For color, coating shall be 5-7 microns epoxy primer on both sides of the sheet and polyester top coat 15-18 microns, using self drilling/tapping SS screws of size 6 x 50mm with 3mm thick EPDM seal and SS plain washer complete : Precoated/mill finish aluminium Ridges plain (500600mm) — is derived from 6 priced inputs for 20.20 metre and works out to ₹1,066.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • One piece plain ridges
  • Consider a shed of 20x10m (external dimensions at plinth)
  • Length of ridges 20.2 metre + 5% wastage =
  • 1.01 metre. Total =23.11 metre.
CodeInputUnitQuantityRate (INR)Amount (INR)
3068Precoated/Mill finish Aluminium plain ridges 0.71 mm TCT/plain and 500600 mm widePrecoated/Mill finish Aluminium plain ridges 0.71 mm TCT/plain and 500- 600 mm wideMaterialmetre23.11576.0013,311.36
9977Carriage (The ridge is to be fixed with the same screws as the Sheets)MaterialL.S.13.522.2730.69
9999SundriesMaterialL.S.6.762.2715.35
0130MistryLabourday0.14897.00125.58
0112Carpenter 2nd classLabourday0.55816.00448.80
0114BeldarLabourday1.64736.001,207.04
Total
15,138.82
Add 1 % Water charges on “W”
151.39
TOTAL
15,290.21
Add GST on “X” (multiplying factor 0.2127)
3,252.23
TOTAL
18,542.44
Add 15% CPOH on “Y”
2,781.37
TOTAL
21,323.81
Add Cess @ 1% on “Z”
213.24
Cost of 20.20 metre
21,537.05
Cost of 1 metre
1,066.19
Say
1,066.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 945. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.