Providing & fixing at all heights, levels and locations Mill finish Aluminium alloy roofing sheets of alloy IS designation 31500, temper Hx8 conforming to IS 737 and dimensions as per IS code 2676 with characteristics of good formability and corrosion resistance. The profile sheets shall be fixed to truss members in slope or required pitch or curvature with Hex cap headed self drilling/tapping Stainless steel screws M6, 50 mm long with 3 mm EPDM seal washer etc. all inclusive of labour, scaffolding, T&P and sundries etc. complete as per directions of the Engineer-In-Charge. (Cost of truss/frame work shall be paid separately)

0.91mm Aluminium Circular (sinusoidal) profile with center to center pitch of 75 mm, depth of 19 mm, overall profile width 1250mm,cover width 1150mm
Item number
12.64.9
Analysis basis
216.14 sqm
Priced inputs
8
Derived rate
₹1,596.45/ SQM
D-01/RATE ANALYSISITEM 12.64.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.64.9 (Providing & fixing at all heights, levels and locations Mill finish Aluminium alloy roofing sheets of alloy IS designation 31500, temper Hx8 conforming to IS 737 and dimensions as per IS code 2676 with characteristics of good formability and corrosion resistance. The profile sheets shall be fixed to truss members in slope or required pitch or curvature with Hex cap headed self drilling/tapping Stainless steel screws M6, 50 mm long with 3 mm EPDM seal washer etc. all inclusive of labour, scaffolding, T&P and sundries etc. complete as per directions of the Engineer-In-Charge. (Cost of truss/frame work shall be paid separately) 0.91mm Aluminium Circular (sinusoidal) profile with center to center pitch of 75 mm, depth of 19 mm, overall profile width 1250mm,cover width 1150mm) is derived from 8 priced inputs for 216.14 sqm and works out to ₹1,596.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consider a shed of 20 x 10 meters.
  • (External dimensions of plinth)
  • Area of roof- 20.20x10.70m = 216.14 sqm.
  • MATERIAL:
  • Sheets used = 18 Nos x 10.70mx1.250m=
  • Total = 240.75sqm.
  • Total = 247.97sqm
  • (per sqm 4 nos) 216.14x4=864.55 no’s
  • LABOUR:
  • Add 3% wastage = 7.22sqm
ANALYSIS OF RATES · ITEM 12.64.9DETAILS OF COST FOR 216.14 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
3059MATAluminium Circular(sinusoidal) profile sheet 0.91mm thick with center to center pitch of 75 mm, depth of 19 mm, overall profile width 1250mm,cover width 1150mmAluminium Circular(sinusoidal) profile sheet 0.91 mm thick with center to center pitch of 75 mm, depth of 19 mm, overall profile width 1250 mm,cover width 1150 mmsqm247.97892.002,21,189.24
9999MATCarriage of sheetsL.S.1042.27236.08
3074MATStainless steel self tapping screw of 6x50mm with SS hex cap and 3mm thick EPDM sealStainless steel self tapping screw of 6x50 mm with SS hex cap and 3 mm thick EPDM seal100 Nos8.65511.004,420.15
9999MATCarriage of screws, washersL.S.8.062.2718.30
9999MATSundriesL.S.39.522.2789.71
0130LABMistryday2.34897.002,098.98
0112LABHelperCarpenter 2nd classday9.34816.007,621.44
0114LABBeldarday9.34736.006,874.24
BUILD-UP TO RATE
Total
2,42,548.14
Add 1 % Water charges on “W”
+2,425.48
TOTAL
2,44,973.62
Add GST on “X” (multiplying factor 0.2127)
+52,105.89
TOTAL
2,97,079.51
Add 15% CPOH on “Y”
+44,561.93
TOTAL
3,41,641.44
Add Cess @ 1% on “Z”
+3,416.41
Cost of 216.14 sqm
3,45,057.85
Cost of 1 sqm
1,596.46
SAY
₹1,596.45
D-02/SOURCEPRINTED PAGE 938
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
938

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 938. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.