Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183 having density 24 kg/m3, 50 mm thick, wrapped in 200G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held in position by criss crossing GI wire etc. complete as per directions of Engineer-in-Charge

Item number
12.57
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹358.50/ SQM
D-01/RATE ANALYSISITEM 12.57

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.57 (Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183 having density 24 kg/m3, 50 mm thick, wrapped in 200G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held in position by criss crossing GI wire etc. complete as per directions of Engineer-in-Charge) is derived from 5 priced inputs for 10 sqm and works out to ₹358.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Area for 10.00sqm. (Finished surface) =
  • 10.00sqm.+
  • Total =11.00sqm
  • Add Wastage @ 10% =1.00 sqm
ANALYSIS OF RATES · ITEM 12.57DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7232MATResin Bonded Glass wool 24 kg/m³ 50 mm thickResin Bonded Glass wool 24 kg/m³ : 50 mm thicksqm11140.001,540.00
9999MATSundries including GL wire 20 SWg and Virgin polythene bags 200 gramL.S.522.27118.04
0111LABCarpenter 1st classday0.5897.00448.50
0114LABBeldarday0.5736.00368.00
9999MATSundries (screws and washers)L.S.202.2745.40
BUILD-UP TO RATE
TOTAL
2,519.94
Add 1 % Water charges on “W”
+25.20
TOTAL
2,545.14
Add GST on “X” (multiplying factor 0.2127)
+541.35
TOTAL
3,086.49
Add 15% CPOH on “Y”
+462.97
TOTAL
3,549.46
Add Cess @ 1% on “Z”
+35.49
Cost of 10 sqm
3,584.95
Cost of 1 sqm
358.50
SAY
₹358.50
D-02/SOURCEPRINTED PAGE 926
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
926

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 926. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.