Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183 having density 24 kg/m3, 50 mm thick, wrapped in 200G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held in position by criss crossing GI wire etc. complete as per directions of Engineer-in-Charge

Item number
12.57
Analysis basis
Details of cost for 10 sqm
Priced inputs
5
Derived rate
358.50 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.57 Providing and fixing thermal insulation with Resin Bonded Fibre glass wool conforming to IS: 8183 having density 24 kg/m3, 50 mm thick, wrapped in 200G Virgin Polythene Bags fixed to wall with screw, rawel plug & washers and held in position by criss crossing GI wire etc. complete as per directions of Engineer-in-Charge — is derived from 5 priced inputs for 10 sqm and works out to ₹358.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Area for 10.00sqm. (Finished surface) =
  • 10.00sqm.+
  • Total =11.00sqm
  • Add Wastage @ 10% =1.00 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
7232Resin Bonded Glass wool 24 kg/m³ 50 mm thickResin Bonded Glass wool 24 kg/m³ : 50 mm thickMaterialsqm11140.001,540.00
9999Sundries including GL wire 20 SWg and Virgin polythene bags 200 gramMaterialL.S.522.27118.04
0111Carpenter 1st classLabourday0.5897.00448.50
0114BeldarLabourday0.5736.00368.00
9999Sundries (screws and washers)MaterialL.S.202.2745.40
TOTAL
2,519.94
Add 1 % Water charges on “W”
25.20
TOTAL
2,545.14
Add GST on “X” (multiplying factor 0.2127)
541.35
TOTAL
3,086.49
Add 15% CPOH on “Y”
462.97
TOTAL
3,549.46
Add Cess @ 1% on “Z”
35.49
Cost of 10 sqm
3,584.95
Cost of 1 sqm
358.50
Say
358.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 926. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.