CPWD Analysis of Rates · Roofing
Providing and fixing tiled false ceiling of specified materials of size 595x595 mm in true horizontal level, suspended on inter locking metal grid of hot dipped galvanized steel sections ( galvanized @ 120 grams/ sqm, both side inclusive) consisting of main “T” runner with suitably spaced joints to get required length and of size 24x38 mm made from 0.30 mm thick (minimum) sheet, spaced at 1200 mm center to center and cross “T” of size 24x25 mm made of 0.30 mm thick (minimum) sheet, 1200 mm long spaced between main “T” at 600 mm center to center to form a grid of 1200x600 mm and secondary cross “T” of length 600 mm and size 24x25 mm made of 0.30 mm thick (minimum) sheet to be interlocked at middle of the 1200x600 mm panel to form grids of 600x600 mm and wall angle of size 24x24x0.3 mm and laying false ceiling tiles of approved texture in the grid including, required cutting/ making, opening for services like diffusers, grills, light fittings, fixtures, smoke detectors etc. Main “T” runners to be suspended from ceiling using GI slotted cleats of size 27 x 37 x 25 x1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm long dash fasteners, 4 mm GI adjustable rods with galvanised butterfly level clips of size 85 x 30 x 0.8 mm spaced at 1200 mm center to center along main T, bottom exposed width of 24 mm of all T-sections shall be pre-painted with polyester paint, all complete for all heights as per specifications, drawings and as directed by Engineer-in-charge
GI Metal Ceiling Lay in perforated Tegular edge global white colour tiles of size 595x595 mm and 0.5 mm thick with 8 mm drop; made of GI sheet having galvanizing of 100 gms/ sqm (both sides inclusive) and 20% perforation area with 1.8 mm dia holes and having NRC (Noise Reduction Coefficient ) of 0.5, electro statically polyester powder coated of thickness 60 microns (minimum), including factory painted after bending and perforation, and backed with a black Glass fiber acoustical fleece
- Item number
- 12.52.2
- Analysis basis
- Details of cost for 100 sqm.
- Priced inputs
- 13
- Derived rate
- ₹2,068.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.52.2 — Providing and fixing tiled false ceiling of specified materials of size 595x595 mm in true horizontal level, suspended on inter locking metal grid of hot dipped galvanized steel sections ( galvanized @ 120 grams/ sqm, both side inclusive) consisting of main “T” runner with suitably spaced joints to get required length and of size 24x38 mm made from 0.30 mm thick (minimum) sheet, spaced at 1200 mm center to center and cross “T” of size 24x25 mm made of 0.30 mm thick (minimum) sheet, 1200 mm long spaced between main “T” at 600 mm center to center to form a grid of 1200x600 mm and secondary cross “T” of length 600 mm and size 24x25 mm made of 0.30 mm thick (minimum) sheet to be interlocked at middle of the 1200x600 mm panel to form grids of 600x600 mm and wall angle of size 24x24x0.3 mm and laying false ceiling tiles of approved texture in the grid including, required cutting/ making, opening for services like diffusers, grills, light fittings, fixtures, smoke detectors etc. Main “T” runners to be suspended from ceiling using GI slotted cleats of size 27 x 37 x 25 x1.6 mm fixed to ceiling with 12.5 mm dia and 50 mm long dash fasteners, 4 mm GI adjustable rods with galvanised butterfly level clips of size 85 x 30 x 0.8 mm spaced at 1200 mm center to center along main T, bottom exposed width of 24 mm of all T-sections shall be pre-painted with polyester paint, all complete for all heights as per specifications, drawings and as directed by Engineer-in-charge GI Metal Ceiling Lay in perforated Tegular edge global white colour tiles of size 595x595 mm and 0.5 mm thick with 8 mm drop; made of GI sheet having galvanizing of 100 gms/ sqm (both sides inclusive) and 20% perforation area with 1.8 mm dia holes and having NRC (Noise Reduction Coefficient ) of 0.5, electro statically polyester powder coated of thickness 60 microns (minimum), including factory painted after bending and perforation, and backed with a black Glass fiber acoustical fleece — is derived from 13 priced inputs for 100 sqm and works out to ₹2,068.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- Celling Area =100 sqm
- Total=100.05 sqm
- Including Wastage @ 10%
- Including Wastage @ 10%
- Including Wastage @ 10% on Grid for cut
- outs
- Including Wastage @ 10% on Grid for cut
- outs
- Add wastage @ 5% = 0.05 sqm.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8600 | GI Metal Tile Lay-in Perforated Tegular edge global white color tiles of Size 595x595mm and 0.5 mm thickGI Metal Tile Lay-in Perforated Tegular edge global white color tiles of size 595x595 mm and 0.5 mm thickMaterial | sqm | 105 | 812.00 | 85,260.00 |
| 8611 | Main T ceiling sections 24x38x0.3 mm (3 metre long)Material | each | 29.5 | 141.00 | 4,159.50 |
| 8612 | Perimeter wall angle 24x24x0.3mm (3 metre long)Perimeter wall angle 24 x 24 x 0.3 mm (3 metre long)Material | each | 13.5 | 87.00 | 1,174.50 |
| 8613 | Intermediate cross T-section 24x25x0.3mm (1.2 mtrs long)Intermediate cross T-Section 24x25x0.3 mm (1.2 m long)Material | each | 147 | 44.00 | 6,468.00 |
| 8614 | Intermediate cross T-section 24x25x 0.3mm (0.6 mtrs long)Intermediate cross T-Section 24x25x0.3 mm (0.6 m long)Material | each | 147 | 22.00 | 3,234.00 |
| 8615 | Hanger rod 4 mm thickMaterial | each | 72 | 11.00 | 792.00 |
| 8616 | Adjustment clip 85x30x0.8mmAdjustment clip 85x30x0.8 mmMaterial | each | 72 | 7.00 | 504.00 |
| 8617 | Soffit cleat (Size 27x37x25x1.60mm)Soffit cleat (Size 27x37x25x1.60 mm)Material | each | 72 | 6.00 | 432.00 |
| 7388 | Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia boltDash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia boltMaterial | each | 72 | 10.00 | 720.00 |
| 9999 | Sundries i.e. scaffolding etc.Material | L.S. | 187.95 | 2.27 | 426.65 |
| 9977 | Carriage of materials etc.Material | L.S. | 89.28 | 2.27 | 202.67 |
| 0111 | Carpenter 1st classLabour | day | 28 | 897.00 | 25,116.00 |
| 0114 | BeldarLabour | day | 23 | 736.00 | 16,928.00 |
- TOTAL
- 1,45,417.32
- Add 1 % Water charges on “W”
- 1,454.17
- TOTAL
- 1,46,871.49
- Add GST on “X” (multiplying factor 0.2127)
- 31,239.57
- TOTAL
- 1,78,111.06
- Add 15% CPOH on “Y”
- 26,716.66
- TOTAL
- 2,04,827.72
- Add Cess @ 1% on “Z”
- 2,048.28
- Cost of 100 sqm.
- 2,06,876.00
- Cost of 1 sqm.
- 2,068.76
- Say
- 2,068.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 918. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works