R/DAR 2023

Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thickness and of approved pattern on steel frame work complete (steel frame work to be paid separately)

Item number
12.49
Analysis basis
3.60 metre
Priced inputs
4
Derived rate
₹96.90/ METRE
D-01/RATE ANALYSISITEM 12.49

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.49 (Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thickness and of approved pattern on steel frame work complete (steel frame work to be paid separately)) is derived from 4 priced inputs for 3.60 metre and works out to ₹96.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 12.49DETAILS OF COST FOR 3.60 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8669MATMangalore ridge tiles 20 mm thickeach1210.00120.00
0123LABMason 1st classMason 1st classday0.01897.008.97
0114LABBeldarday0.15736.00110.40
9999MATSundriesL.S.2.62.275.90
BUILD-UP TO RATE
TOTAL
245.27
Add 1 % Water charges on “W”
+2.45
TOTAL
247.72
Add GST on “X” (multiplying factor 0.2127)
+52.69
TOTAL
300.41
Add 15% CPOH on “Y”
+45.06
TOTAL
345.47
Add Cess @ 1% on “Z”
+3.45
Cost of 3.60 metre
348.92
Cost for 1 metre
96.92
SAY
₹96.90
D-02/SOURCEPRINTED PAGE 912
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
912

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 912. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING