CPWD Analysis of Rates · Roofing
Extra for straight cutting in C.G.S. sheet roofing for making opening of area exceeding 40 sq. decimeter for chimney stacks, sky light etc.
0.63 mm thick
- Item number
- 12.2.3
- Analysis basis
- Details of cost for 3 metres periphery
- Priced inputs
- 2
- Derived rate
- ₹92.95 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.2.3 — Extra for straight cutting in C.G.S. sheet roofing for making opening of area exceeding 40 sq. decimeter for chimney stacks, sky light etc.: 0.63 mm thick — is derived from 2 priced inputs for 3 metres and works out to ₹92.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Assuming a hole of 10dmx5dm area of the
- hole 50dm2 and the perimeter of the hole 3
- metre
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0102 | Blacksmith 1st classLabour | day | 0.12 | 897.00 | 107.64 |
| 0114 | BeldarLabour | day | 0.12 | 736.00 | 88.32 |
- TOTAL
- 195.96
- Add 1 % Water charges on “W”
- 1.96
- TOTAL
- 197.92
- Add GST on “X” (multiplying factor 0.2127)
- 42.10
- TOTAL
- 240.02
- Add 15% CPOH on “Y”
- 36.00
- TOTAL
- 276.02
- Add Cess @ 1% on “Z”
- 2.76
- Cost of 3.00 metres
- 278.78
- Cost of 1.00 metre
- 92.93
- Say
- 92.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 856. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.