Skip to main content
R/DAR 2023

Extra for straight cutting in C.G.S. sheet roofing for making opening of area exceeding 40 sq. decimeter for chimney stacks, sky light etc.

1.00 mm thick
Item number
12.2.1
Analysis basis
3 metres
Priced inputs
2
Derived rate
₹116.15/ METRE
D-01/RATE ANALYSISITEM 12.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.2.1 (Extra for straight cutting in C.G.S. sheet roofing for making opening of area exceeding 40 sq. decimeter for chimney stacks, sky light etc.: 1.00 mm thick) is derived from 2 priced inputs for 3 metres and works out to ₹116.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Assuming a hole of 10dmx5dm area of the
  • hole 50dm2 and the perimeter of the hole 3
  • metre
ANALYSIS OF RATES · ITEM 12.2.1DETAILS OF COST FOR 3 METRES PERIPHERY
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0102LABBlacksmith 1st classday0.15897.00134.55
0114LABBeldarday0.15736.00110.40
BUILD-UP TO RATE
TOTAL
244.95
Add 1 % Water charges on “W”
+2.45
TOTAL
247.40
Add GST on “X” (multiplying factor 0.2127)
+52.62
TOTAL
300.02
Add 15% CPOH on “Y”
+45.00
TOTAL
345.02
Add Cess @ 1% on “Z”
+3.45
Cost of 3.00 metres
348.47
Cost of 1.00 metre
116.16
SAY
₹116.15
D-02/SOURCEPRINTED PAGE 855
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
855

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 855. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.