CPWD Analysis of Rates · Road Work
Providing and laying factory made chamfered edge Cement Concrete paver blocks in footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand. complete all as per direction of Engineer-in-Charge
60mm thick cement concrete paver block of M-35 grade with approved colour, design & pattern
- Item number
- 16.91.1
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 8
- Derived rate
- ₹1,045.65 / Sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.91.1 — Providing and laying factory made chamfered edge Cement Concrete paver blocks in footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand. complete all as per direction of Engineer-in-Charge 60mm thick cement concrete paver block of M-35 grade with approved colour, design & pattern — is derived from 8 priced inputs for 10 sqm and works out to ₹1,045.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7773 | Coloured C.C. inter locking paver Block (60 mm thick, M-35) (including carriage)Coloured C.C. inter locking paver Block (60 mm thick, M-35) (including carriage)Material | sqm | 10 | 450.00 | 4,500.00 |
| 0982 | Coarse sand (zone-III)Coarse sand (zone III)Material | cum | 0.5 | 1,450.00 | 725.00 |
| 0983 | Fine sand (zone IV)Material | cum | 0.11 | 980.00 | 107.80 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.5 | 897.00 | 448.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
| 0115 | CoolieLabour | day | 0.5 | 736.00 | 368.00 |
| 9999 | SundriesMaterial | L.S. | 25 | 2.27 | 56.75 |
- TOTAL
- 7,350.05
- Add 1 % Water charges on “W”
- 73.50
- TOTAL
- 7,423.55
- Add GST on “X” (multiplying factor 0.2127)
- 1,578.99
- TOTAL
- 9,002.54
- Add 15% CPOH on “Y”
- 1,350.38
- TOTAL
- 10,352.92
- Add Cess @ 1% on “Z”
- 103.53
- Cost of 10 Sqm
- 10,456.45
- Cost of 1 Sqm
- 1,045.65
- Say
- 1,045.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1273. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works