Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge

40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in drum Type Hot Mix Plant of 60-90 TPH capacity
Item number
16.57.5
Analysis basis
191 cum
Priced inputs
18
Derived rate
₹12,026.80/ CUM
D-01/RATE ANALYSISITEM 16.57.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.57.5 (Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in drum Type Hot Mix Plant of 60-90 TPH capacity) is derived from 18 priced inputs for 191 cum and works out to ₹12,026.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • @5.50% (percentage by weight of total mix
  • Aggregate
  • Total weight of mix = 450 tonnes
  • Weight of bitumen = 24.75 tonnes
  • Weight of aggregate = 450 -24.75 = 425.25
  • tonnes
  • Taking density of aggregate = 1.5 tonne/cum
  • Volume of aggregate =425.25/1.5
  • =283.50cum
  • Grading - II/19 mm (Nominal Size)
  • 13.2 - 10mm size = 30% of 283.50 = 85.05 cum
  • 10 - 5mm size = 25% of 283.50 = 70.88 cum
  • 5mm and below = 42% of 283.50 = 119.07 cum
  • Qty = 85.05 * 50 /100
  • Qty = 85.05 * 50 /100
  • Qty = 70.88 * 50 /100
  • Qty = 70.88 * 50 /100
  • Qty = 283.5 * 40 /100
  • Lime Filler @ 2% ( percentage by weight of
  • aggregate)
  • Topper 10 tonne capacity (Taken 10km
  • avarage lead)
  • 450x10=4500 tonne km
  • for initial break down rolling.(6*0.65)
  • for intermediate rolling.(6*0.65)
  • Finish rolling with 6-8 tonnes smooth
  • wheeled tandem roller.(6*0.65)
  • working with HMP, mechanical broom,
  • paver, roller, asphalt cutter and assistance
  • for setting out lines, levels and layout of
  • construction
  • for checking line & levels
ANALYSIS OF RATES · ITEM 16.57.5DETAILS OF COST FOR 191 CUM (450 TONNES)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7309MATPaving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualitytonne24.7541,202.0010,19,749.50
0296MATStone Aggregate (Single size) : 12.5 mm nominal sizecum42.5251,400.0059,535.00
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum42.5251,400.0059,535.00
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum35.441,400.0049,616.00
0298MATStone Aggregate (Single size) : 06 mm nominal sizecum35.441,425.0050,502.00
2903MATStone chippings/ screenings 4.75 mm nominal sizecum119.071,600.001,90,512.00
0777MATDry hydrated lime (factory made)quintal127.6315.0040,194.00
0076MACHDrum Type HMP of 60-90 TPH capacity @ 75 tonne per hour actual outputhour613,450.0080,700.00
0064MACHPaver finisher Hydrostatic with sensor control 100 TPHhour61,700.0010,200.00
0069MACHGenerator 250 KVAhour6450.002,700.00
0052MACHFront end loader 1 cum bucket capacity (incl POL)hour61,450.008,700.00
0053MACHTipper -5 CumTipper-5 Cum/10 tonnestonne km4,5003.7016,650.00
0055MACHSmooth Wheeled Roller 8 to 10 tonnehour3.9350.001,365.00
0054MACHVibratory roller 8 to 10 tonnehour3.9700.002,730.00
0056MACHTandem Road Rollerhour3.91,350.005,265.00
0128LABMateday0.84816.00685.44
0114LABBeldarday14736.0010,304.00
0139LABSkilled Beldar (for floor rubbing etc.)day5816.004,080.00
BUILD-UP TO RATE
Add 10 per cent of cost of carriage to cover cost of loading and unloading
+1,665.00
TOTAL
16,14,687.94
Add 1 % Water charges on “W”
+16,146.88
TOTAL
16,30,834.82
Add GST on “X” (multiplying factor 0.2127)
+3,46,878.57
TOTAL
19,77,713.39
Add 15% CPOH on “Y”
+2,96,657.01
TOTAL
22,74,370.40
Add Cess @ 1% on “Z”
+22,743.70
Cost for 191 cum(450 Tonne)
22,97,114.10
Cost per cum.
12,026.78
SAY
₹12,026.80
D-02/SOURCEPRINTED PAGE 1236
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1236

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1236. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.