Skip to main content

CPWD Analysis of Rates · Road Work

Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge

40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity

Item number
16.57.1
Analysis basis
Details of cost for 191 cum (450 tonnes)
Priced inputs
19
Derived rate
12,126.20 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.57.1 Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity — is derived from 19 priced inputs for 191 cum and works out to ₹12,126.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • @5.50% (percentage by weight of total mix
  • Aggregate
  • Total weight of mix = 450 tonnes
  • Weight of bitumen = 24.75 tonnes
  • Weight of aggregate = 450 -24.75 =
  • 425.25 tonnes
  • Taking density of aggregate = 1.5 tonne/cum
  • Volume of aggregate =425.25/1.5
  • =283.50cum
  • Grading - II/19 mm (Nominal Size)
  • 13.2 - 10mm size = 30% of 283.50 = 85.05 cum
  • 10 - 5mm size = 25% of 283.50 = 70.88 cum
  • 5mm and below = 42% of 283.50 =119.07 cum
  • Waste Plastic @ 8% of the weigh of bitumen
  • i.e. 24.75*8%
  • Qty = 85.05 * 50 /100
  • Qty = 85.05 * 50 /100
  • Qty = 70.88 * 50 /100
  • Qty = 70.88 * 50 /100
  • Qty = 283.5 * 40 /100
  • Lime Filler @ 2% ( percentage by weight of
  • aggregate)
  • Topper 10 tonne capacity (Taken 10km
  • avarage lead)
  • 450x10=4500 tonne km
  • Topper 10 tonne capacity (Taken 10km
  • avarage lead)
  • 450x10=4500 tonne km
  • for initial break down rolling.(6*0.65)
  • for intermediate rolling.(6*0.65)
  • Finish rolling with 6-8 tonnes smooth
  • wheeled tandem roller.(6*0.65)
  • working with HMP, mechanical broom,
  • paver, roller, asphalt cutter and assistance
  • for setting out lines, levels and layout of
  • construction
  • for checking line & levels
CodeInputUnitQuantityRate (INR)Amount (INR)
7309Paving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualityMaterialtonne24.7541,202.0010,19,749.50
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum42.5251,400.0059,535.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum42.5251,400.0059,535.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum35.441,400.0049,616.00
0298Stone Aggregate (Single size) : 06 mm nominal sizeMaterialcum35.441,425.0050,502.00
2903Stone chippings/ screenings 4.75 mm nominal sizeMaterialcum119.071,600.001,90,512.00
0777Dry hydrated lime (factory made)Materialquintal127.6315.0040,194.00
0062Hot mix Plant -120 TPH capacityMachineryhour316,800.0050,400.00
0063Hot mix Plant 100 TPH CapacityMachineryhour314,550.0043,650.00
0064Paver finisher Hydrostatic with sensor control 100 TPHMachineryhour61,700.0010,200.00
0069Generator 250 KVAMachineryhour6450.002,700.00
0052Front end loader 1 cum bucket capacity (incl POL)Machineryhour61,450.008,700.00
0053Tipper -5 CumTipper-5 Cum/10 tonnesMachinerytonne km4,5003.7016,650.00
0055Smooth Wheeled Roller 8 to 10 tonneMachineryhour3.9350.001,365.00
0054Vibratory roller 8 to 10 tonneMachineryhour3.9700.002,730.00
0056Tandem Road RollerMachineryhour3.91,350.005,265.00
0128MateLabourday0.84816.00685.44
0114BeldarLabourday14736.0010,304.00
0139Skilled Beldar (for floor rubbing etc.)Labourday5816.004,080.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading
1,665.00
TOTAL
16,28,037.94
Add 1 % Water charges on “W”
16,280.38
TOTAL
16,44,318.32
Add GST on “X” (multiplying factor 0.2127)
3,49,746.51
TOTAL
19,94,064.83
Add 15% CPOH on “Y”
2,99,109.72
TOTAL
22,93,174.55
Add Cess @ 1% on “Z”
22,931.75
Cost for 191 cum(450 Tonne)
23,16,106.30
Cost per cum.
12,126.21
Say
12,126.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1230. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works