Providing and laying semidense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge

25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity

Item number
16.56.1
Analysis basis
Details of cost for 195 cum (450 tonnes)
Priced inputs
16
Derived rate
277.70 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.56.1 Providing and laying semidense Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge 25 mm compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity — is derived from 16 priced inputs for 195 cum and works out to ₹277.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Area covered for 25 mm thickness=7800
  • sqm
  • 5% of 450 MT = 22.50 MT
  • Weight of mix = 205 * 2.5 = 450 tonnes
  • Aggregate
  • Total weight of mix = 450 tonnes Weight of
  • bitumen = 15.75 tonnes
  • Weight of aggregate = 450 -15.75 = 434.25
  • tonnes
  • Taking density of aggregate = 1.5 tonne/cum
  • Volume of aggregate =434.25/1.5
  • =289.50cum
  • Grading - II/19 mm (Nominal Size)
  • 25 - 10mm size = 40% of 289.50 = 115.8 cum
  • 10 - 5mm size = 40% of 289.50 = 115.8 cum
  • 5mm and below = 20% of 289.50 = 57.9 cum
  • Qty = 162.45 * 50 /100
  • Qty = 162.45 * 50 /100
  • Qty = 285 * 41 /100
  • Lime Filler @ 2% ( percentage by weight of
  • aggregate)
  • @75tonne per hour actual output
  • @75tonne per hour actual output
  • @75tonne per hour actual output
  • Topper 10 tonne capacity (Taken 10km
  • avarage lead)
  • 450x10=4500 tonne km
  • for initial break down rolling.(6*0.65)
  • for intermediate rolling.(6*0.65)
  • Finish rolling with 6-8 tonnes smooth
  • wheeled tandem roller.(6*0.65)
  • working with HMP, mechanical broom,
  • paver, roller, asphalt cutter and assistance
  • for setting out lines, levels and layout of
  • construction for checking line & levels
CodeInputUnitQuantityRate (INR)Amount (INR)
7309Paving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualityMaterialtonne22.541,202.009,27,045.00
0296Stone Aggregate (Single size) : 12.5 mm nominal sizeMaterialcum81.2251,400.001,13,715.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum81.2251,400.001,13,715.00
2903Stone chippings/ screenings 4.75 mm nominal size nominal sizeStone chippings/ screenings 4.75 mm nominal sizeMaterialcum116.851,600.001,86,960.00
0777Dry hydrated lime (factory made)Materialquintal85.5315.0026,932.50
0062Hot mix Plant -120 TPH capacityMachineryhour316,800.0050,400.00
0063Hot mix Plant 100 TPH CapacityMachineryhour314,550.0043,650.00
0064Paver finisher Hydrostatic with sensor control 100 TPHMachineryhour61,700.0010,200.00
0069Generator 250 KVAMachineryhour6450.002,700.00
0052Front end loader 1 cum bucket capacity (incl POL)Machineryhour61,450.008,700.00
0053Tipper -5 CumTipper-5 Cum/10 tonnesMachinerytonne km4,5003.7016,650.00
0055Smooth Wheeled Roller 8 to 10 tonneMachineryhour3.9350.001,365.00
0054Vibratory roller 8 to 10 tonneMachineryhour3.9700.002,730.00
0056Tandem Road RollerMachineryhour3.91,350.005,265.00
0128MateLabourday0.84816.00685.44
0114BeldarLabourday14736.0010,304.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading
1,665.00
TOTAL
15,22,681.94
Add 1 % Water charges on “W”
15,226.82
TOTAL
15,37,908.76
Add GST on “X” (multiplying factor 0.2127)
3,27,113.19
TOTAL
18,65,021.95
Add 15% CPOH on “Y”
2,79,753.29
TOTAL
21,44,775.24
Add Cess @ 1% on “Z”
21,447.75
Cost for 7800 Sqm
21,66,222.99
Cost per sqm
277.72
Say
277.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1227. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.