Providing and laying bituminous macadam using crushed stone aggregates of specified grading premixed with bituminous binder, transported to site by tippers, laid over a previously prepared surface with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specificatons and directions of Engineer-in-Charge

50 to 100 mm average compacted thickness with bitumen of grade VG-30 @ 3.50% (percentage by weight of total mix) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity

Item number
16.55.1
Analysis basis
Details of cost for 205 cum (or 450 M.T. )
Priced inputs
18
Derived rate
8,505.65 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.55.1 Providing and laying bituminous macadam using crushed stone aggregates of specified grading premixed with bituminous binder, transported to site by tippers, laid over a previously prepared surface with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specificatons and directions of Engineer-in-Charge 50 to 100 mm average compacted thickness with bitumen of grade VG-30 @ 3.50% (percentage by weight of total mix) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity — is derived from 18 priced inputs for 205 cum and works out to ₹8,505.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • 3.5% of 450 MT = 15.75 MT
  • Weight of mix = 205 * 2.5 = 450 tonnes
  • Aggregate
  • Total weight of mix = 450 tonnes Weight of
  • bitumen = 15.75 tonnes Weight of
  • aggregate = 450 -15.75 = 434.25 tonnes
  • Taking density of aggregate = 1.5 tonne/cum
  • Volume of aggregate =434.25/1.5
  • =289.50cum
  • Grading - II/19 mm (Nominal Size)
  • 25 - 10mm size = 40% of 289.50 = 115.8 cum
  • 10 - 5mm size = 40% of 289.50 = 115.8 cum
  • 5mm and below = 20% of 289.50 = 57.9 cum
  • Qty = 115.8 * 50 /100
  • Qty = 115.8 * 50 /100
  • Qty = 115.8 * 50 /100
  • Qty = 115.8 * 50 /100
  • Qty = 289.50 * 20 /100
  • @75tonne per hour actual output
  • @75tonne per hour actual output
  • @75tonne per hour actual output
  • Topper 10 tonne capacity (Taken 10km
  • avarage lead)
  • 450x10=4500 tonne km
  • for initial break down rolling.(6*0.65)
  • for intermediate rolling.(6*0.65)
  • Finish rolling with 6-8 tonnes smooth
  • wheeled tandem roller.(6*0.65)
  • working with HMP, mechanical broom,
  • paver, roller, asphalt cutter and assistance
  • for setting out lines, levels and layout of
  • construction
  • for checking line & levels
CodeInputUnitQuantityRate (INR)Amount (INR)
7309Paving Asphalt VG-30 of approved qualityPaving Asphalt of grade VG-30 of approved qualityMaterialtonne15.7541,202.006,48,931.50
0294Stone Aggregate (Single size) : 25 mm nominal sizeMaterialcum57.91,400.0081,060.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum57.91,400.0081,060.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum57.91,400.0081,060.00
0298Stone Aggregate (Single size) : 06 mm nominal sizeMaterialcum57.91,425.0082,507.50
2903Stone chippings/ screenings 4.75 mm nominal sizeMaterialcum57.91,600.0092,640.00
0062Hot mix Plant -120 TPH capacityMachineryhour316,800.0050,400.00
0063Hot mix Plant 100 TPH CapacityMachineryhour314,550.0043,650.00
0064Paver finisher Hydrostatic with sensor control 100 TPHMachineryhour61,700.0010,200.00
0069Generator 250 KVAMachineryhour6450.002,700.00
0052Front end loader 1 cum bucket capacity (incl POL)Machineryhour61,450.008,700.00
0053Tipper -5 CumTipper-5 Cum/10 tonnesMachinerytonne/km4,5003.7016,650.00
0055Smooth Wheeled Roller 8 to 10 tonneMachineryhour3.9350.001,365.00
0054Vibratory roller 8 to 10 tonneMachineryhour3.9700.002,730.00
0056Tandem Road RollerMachineryhour3.91,350.005,265.00
0128MateLabourday0.84816.00685.44
0114BeldarLabourday14736.0010,304.00
0139Skilled Beldar (for floor rubbing etc.)Labourday5816.004,080.00
Add 10 per cent of cost of carriage to cover cost of loading and unloading
1,665.00
TOTAL
12,25,653.44
Add 1 % Water charges on “W”
12,256.53
TOTAL
12,37,909.97
Add GST on “X” (multiplying factor 0.2127)
2,63,303.45
TOTAL
15,01,213.42
Add 15% CPOH on “Y”
2,25,182.01
TOTAL
17,26,395.43
Add Cess @ 1% on “Z”
17,263.95
Cost for 205 cum(450 M.T.)
17,43,659.38
Cost per cum.
8,505.66
Say
8,505.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1223. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.