Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With medium setting bitumen emulsion

On bituminous surface @ 0.25kg/sqm
Item number
16.31.2.2
Analysis basis
3500 sqm
Priced inputs
6
Derived rate
₹14.05/ SQM
D-01/RATE ANALYSISITEM 16.31.2.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.31.2.2 (Providing and applying tack coat using bitumen emulsion conforming to IS:8887, using emulsion pressure distributer including preparing the surface & cleaning with mechanical broom With medium setting bitumen emulsion On bituminous surface @ 0.25kg/sqm) is derived from 6 priced inputs for 3500 sqm and works out to ₹14.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.31.2.2DETAILS OF COST FOR 3500 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7742MATBitumen emulsion medium setting (M.S.) conforming to IS : 8887-1995Bitumen emulsion medium setting (M.S.) conforming to IS : 8887tonne0.87533,530.0029,338.75
0075MACHRoad sweeper (Mechamical Broom) @ 1250 sqm. Per hourRoad sweeper (Mechamical Broom) @ 1250 sqm per hourhour2.8500.001,400.00
0058MACHAir compressorhour2.8250.00700.00
0061MACHEmulsion Pressure Distributor @ 1750 sqm per hourEmulsion Pressure Distributor of capacity 1750 sqm per hourhour2800.001,600.00
0128LABMateday0.08816.0065.28
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
TOTAL
34,576.03
Add 1 % Water charges on “W”
+345.76
TOTAL
34,921.79
Add GST on “X” (multiplying factor 0.2127)
+7,427.86
TOTAL
42,349.65
Add 15% CPOH on “Y”
+6,352.45
TOTAL
48,702.10
Add Cess @ 1% on “Z”
+487.02
Cost for 3500 sqm.
49,189.12
Cost per Sqm.
14.05
SAY
₹14.05
D-02/SOURCEPRINTED PAGE 1181
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1181

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1181. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.