Skip to main content
R/DAR 2023

Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer, 3 mm thick water proofing membrane, black finished reinforced with glass fibre matt consisting of a coat of bitumen primer for bitumen membrane @ 0.40 litre/sqm by the same membrane manufactured of density at 25°C, 0.87 - 0.89 kg/litre and viscocity 70 - 160 cps. Over the primer coat the layer of membrane shall be laid using butane torch and sealing all joints etc., and preparing the surface complete. The vital physical and chemical parameters of the membrane shall be as under : Joint strength in longitudinal and transverse direction at 23°C as 350/300 N/5 cm. Tear strength in longitudinal and transverse direction as 60/80N. Softening point of membrane not less than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of membrane shall be got done through the authorised applicator of the manufacturer of membrane

3 mm thick
Item number
14.90.1
Analysis basis
30 sqm
Priced inputs
9
Derived rate
₹537.45/ SQM
D-01/RATE ANALYSISITEM 14.90.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.90.1 (Providing and laying APP (Atactic Polypropylene Polymer) modified prefabricated five layer, 3 mm thick water proofing membrane, black finished reinforced with glass fibre matt consisting of a coat of bitumen primer for bitumen membrane @ 0.40 litre/sqm by the same membrane manufactured of density at 25°C, 0.87 - 0.89 kg/litre and viscocity 70 - 160 cps. Over the primer coat the layer of membrane shall be laid using butane torch and sealing all joints etc., and preparing the surface complete. The vital physical and chemical parameters of the membrane shall be as under : Joint strength in longitudinal and transverse direction at 23°C as 350/300 N/5 cm. Tear strength in longitudinal and transverse direction as 60/80N. Softening point of membrane not less than 150°C. Cold flexibility shall be upto -2°C when tested in accordance with ASTM, D - 5147. The laying of membrane shall be got done through the authorised applicator of the manufacturer of membrane : 3 mm thick) is derived from 9 priced inputs for 30 sqm and works out to ₹537.45 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • A.P.P. modified 3 mm thick = 30 sqm
  • Total = 33 sqm
  • Add 10% for wastage - 3 sqm
ANALYSIS OF RATES · ITEM 14.90.1DETAIL OF COST FOR 30 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8204MATA.P.P. modified 3 mm thick membrance reinforced with glass fibre mattA.P.P. modified 3 mm thick membrane reinforced with glass fibre mattsqm33145.004,785.00
8206MATBitumen primer for bitumen membranceBitumen primer for bitumen membranelitre1295.001,140.00
9977MATCarriage of bitumen membranceL.S.7.82.2717.71
1241MATCommercial LPG in cylinderkg7106.00742.00
9999MATPreparing roof surface, cutting groovesL.S.49.532.27112.43
0159LABSkilled torch operator for laying tackday2.16897.001,937.52
0130LABMistryday0.18897.00161.46
0114LABBeldarday3.24736.002,384.64
9999MATSundries, brushes, bitumen torch etcL.S.23.42.2753.12
BUILD-UP TO RATE
TOTAL
11,333.88
Add 1 % Water charges on “W”
+113.34
TOTAL
11,447.22
Add GST on “X” (multiplying factor 0.2127)
+2,434.82
TOTAL
13,882.04
Add 15% CPOH on “Y”
+2,082.31
TOTAL
15,964.35
Add Cess @ 1% on “Z”
+159.64
Cost for 30 sqm
16,123.99
Cost for 1 sqm
537.47
SAY
₹537.45
D-02/SOURCEPRINTED PAGE 1094
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1094

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1094. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSREPAIRS TO BUILDINGS
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.