R/DAR 2023

Providing and laying in situ five course water proofing treatment with APP (Atactic Polypropylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40 litre per sqm, 2nd & 4th courses of bonding material @ 1.20 kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd layer of roofing membrane APP modified Polymeric membrane 2.0 mm thick of 3.00 Kg/ sqm weight consisting of five layers prefabricated with centre core as 100 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 5th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately)

Item number
14.87
Analysis basis
30 sqm
Priced inputs
10
Derived rate
₹532.05/ SQM
D-01/RATE ANALYSISITEM 14.87

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.87 (Providing and laying in situ five course water proofing treatment with APP (Atactic Polypropylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40 litre per sqm, 2nd & 4th courses of bonding material @ 1.20 kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd layer of roofing membrane APP modified Polymeric membrane 2.0 mm thick of 3.00 Kg/ sqm weight consisting of five layers prefabricated with centre core as 100 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 5th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately)) is derived from 10 priced inputs for 30 sqm and works out to ₹532.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • APP modified polymeric felt (two layers) 2.0
  • mm thick = 30 sqm
  • Total = 33 sqm
  • 0.4x30 = 12
  • 1.20x30x2 =72 kg = 0.072 tonne
  • Add 10% wastage = 3 sqm
ANALYSIS OF RATES · ITEM 14.87DETAILS OF COST FOR 30 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8201MATA.P.P. modified polymeric felt (two layers) 2 mm thicksqm33130.004,290.00
0316MATBitumen solution primer of approved qualitylitre1250.00600.00
0313MATBlown type petroleum bitumen of penetration 85/25 of approved qualitytonne0.07238,250.002,754.00
9977MATCarriage of polymeric feltL.S.7.82.2717.71
0370MATCoal (steam)quintal0.174500.0087.00
9999MATPreparing roof surface, cutting grooves and making good the sameL.S.134.552.27305.43
0131LABPainterday1.58816.001,289.28
0114LABBeldarday2.37736.001,744.32
0130LABMistryday0.13897.00116.61
9999MATSundries, brushes etcL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
11,219.70
Add 1 % Water charges on “W”
+112.20
TOTAL
11,331.90
Add GST on “X” (multiplying factor 0.2127)
+2,410.30
TOTAL
13,742.20
Add 15% CPOH on “Y”
+2,061.33
TOTAL
15,803.53
Add Cess @ 1% on “Z”
+158.04
Cost for 30 sqm
15,961.57
Cost for 1 sqm
532.05
SAY
₹532.05
D-02/SOURCEPRINTED PAGE 1091
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1091

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1091. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.