Providing and fixing bright finished brass quadrant stay 300 mm long with necessary brass screws etc. complete
- Item number
- 14.38
- Analysis basis
- 10 nos
- Priced inputs
- 4
- Derived rate
- ₹191.45/ NOS
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.38 (Providing and fixing bright finished brass quadrant stay 300 mm long with necessary brass screws etc. complete) is derived from 4 priced inputs for 10 nos and works out to ₹191.45 each after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0427 | MAT | Brass quadrant stays 300 mm | each | 10 | 121.00 | 1,210.00 |
| 0452 | MAT | Brass screws 25 mm | 100 Nos | 0.4 | 110.00 | 44.00 |
| 9977 | MAT | Carriage of material | L.S. | 0.91 | 2.27 | 2.07 |
| 0111 | LAB | Carpenter 1st class | day | 0.1 | 897.00 | 89.70 |
- TOTAL
- 1,345.77
- Add 1 % Water charges on “W”
- +13.46
- TOTAL
- 1,359.23
- Add GST on “X” (multiplying factor 0.2127)
- +289.11
- TOTAL
- 1,648.34
- Add 15% CPOH on “Y”
- +247.25
- TOTAL
- 1,895.59
- Add Cess @ 1% on “Z”
- +18.96
- Cost of 10 quadrant stayes
- 1,914.55
- Cost of each
- 191.46
- SAY
- ₹191.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1077
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1077. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.