CPWD Analysis of Rates · Repairs to Buildings
Providing and fixing bright finished brass quadrant stay 300 mm long with necessary brass screws etc. complete
- Item number
- 14.38
- Analysis basis
- Details of cost for 10 nos.
- Priced inputs
- 4
- Derived rate
- ₹191.45 / nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 14.38 — Providing and fixing bright finished brass quadrant stay 300 mm long with necessary brass screws etc. complete — is derived from 4 priced inputs for 10 nos and works out to ₹191.45 each after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0427 | Brass quadrant stays 300 mmMaterial | each | 10 | 121.00 | 1,210.00 |
| 0452 | Brass screws 25 mmMaterial | 100 Nos | 0.4 | 110.00 | 44.00 |
| 9977 | Carriage of materialMaterial | L.S. | 0.91 | 2.27 | 2.07 |
| 0111 | Carpenter 1st classLabour | day | 0.1 | 897.00 | 89.70 |
- TOTAL
- 1,345.77
- Add 1 % Water charges on “W”
- 13.46
- TOTAL
- 1,359.23
- Add GST on “X” (multiplying factor 0.2127)
- 289.11
- TOTAL
- 1,648.34
- Add 15% CPOH on “Y”
- 247.25
- TOTAL
- 1,895.59
- Add Cess @ 1% on “Z”
- 18.96
- Cost of 10 quadrant stayes
- 1,914.55
- Cost of each
- 191.46
- Say
- 191.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1077. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.